Status

Halcyon Tower I - Casting of Ground floor Slab - Status as of 3rd December 2020

EDEN B03 Tower A - on casting of 8th floor slab – Status as of 1st December 2020

Tranquil - Retaining wall raft: 213/625 meters & Retaining Wall: 160/625 meter Completed. Total footings for K,L,M,N,O,P & Q towers – 93/419 No's completed. Tower Q - 47/47 footings completed. Columns – 39/551 No’s completed; PCC – 2000/6217 Sq.m - Status as of November 2020

Brigade Cornerstone Utopia Serene Towers – View from central spine - Status as of November 2020

Serene Tower A - 16th Floor slab structure works in progress & Serene Tower B - 15th Floor slab structure works in progress spine - Status as of November 2020

Serene Tower C – 14th Floor slab structure works in progress & Serene Tower D – 16th Floor slab structure works in progress - Status as of November 2020

Serene Tower E - 18th Floor slab structure works in progress & Serene Tower F - 18th Floor slab structure works in progress spine - Status as of November 2020

Serene Tower G - 18th Floor slab structure works in progress & Serene Tower H - 19th Floor slab structure works in progress - Status as of November 2020

Serene Tower C - E Low-rise : Serene Tower C & E Terrace slab completed - Status as of November 2020

Serene Tower E & G - 7th Floor slab structure works in progress - Status as of November 2020

Arcadia - Retaining wall raft – 180/375 Rmt  & Retaining wall – 180/375 Rmt completed. Footings : 57/121 No's completed & 36/139 No's column completed. Tower area footing PCC of 2600/2725 Sq. m completed – Status as of November 2020

Halcyon Tower I : Ground Floor slab work in progress & Tower J : First Basement slab work in progress - Status as of November 2020

Oasis - Ground Floor 1195 / 2300 Sq. m completed – Status as of November 2020

Eden Tower A - 9th Floor structure works under progress - Status as of November 2020

Eden Tower B – 4th Floor slab completed - Status as of November 2020

Eden Tower C – 12th & 13th Floor structure works under progress - Status as of November 2020

Eden Tower D – 5th Floor structure works under progress - Status as of November 2020

Eden Tower E – 12th Floor structure works under progress - Status as of November 2020

Eden Tower B - On Casting of fourth floor slab Completion - 30th November 2020

Tranquil Tower Q - Milestone - On Casting of Footing/raft – Status as of 23rd November 2020

Tranquil Tower Q - Milestone - On Casting of Footing/raft – Status as of 23rd November 2020

Tranquil Tower Q - Milestone - On Casting of Footing/raft – Status as of 23rd November 2020

Serene Wing G - On Casting of Sixteenth floor slab - Status as of 21st November 2020

Serene Wing F - On Casting of Sixteenth floor slab – Status as of 18th November 2020

Serene Wing E - On Casting of Sixteenth floor slab – Status as of 17th November 2020

Halcyon Tower J - On casting of Basement 2 floor Slab – Status as of 6th November 2020

Serene Wing C - On Casting of Twelfth floor slab - Status as of 3rd November 2020

Serene Towers Front view - Status as of October 2020

Serene Tower A - 14th Floor slab structure works in progress. Serene Tower B - 13th Floor slab structure in progress - Status as of October 2020

Serene Tower C - 12th Floor slab structure works in progress. Serene Tower C & D - 14th Floor slab structure works in progress - Status as of October 2020

Serene Tower E - 14th Floor slab structure works completed. Serene Tower F - 15th Floor structure works completed - Status as of October 2020

Serene Tower G - 14th Floor slab structure works completed. Serene Tower H - 16th Floor slab structure works completed - Status as of October 2020

Serene Tower C - E Low rise 9th Floor slab structure works completed - Status as of October 2020

Serene Tower E - G Low Rise 5th Floor slab structure works in progress - Status as of October 2020

Eden Tower A - 6th & 7th Floor structure works under progress - Status as of October 2020

Eden Tower B – 3rd Floor structure works under progress - Status as of October 2020

Eden Tower C - 11th Floor structure works under progress - Status as of October 2020

Eden Tower D - 5th Floor structure works under progress - Status as of October 2020

Eden Tower - E 10th Floor structure works under progress - Status as of October 2020

Serene B05 Tower / Wing H - On Casting of 16th Floor Slab - Status as of October 29th 2020

Eden Wing B - On Casting of Second Floor slab - Status as of 17th October 2020

Serene Wing B - On Casting of Twelfth floor slab - Status as of 17th October 2020

Serene Wing B - On Casting of Twelfth floor slab - Status as of 17th October 2020

Halcyon Tower I - On Casting of first basement slab - October 10th 2020

Oasis GF 670 / 2670 Sqm completed - Status as of October 2020

Oasis GF 670 / 2670 Sqm completed - Status as of October 2020

Halcyon Tower I Basement – 02 floor slab - 100% completed. Halcyon Tower I Basement - 01 floor slab - 50% completed. And Halcyon Tower J Basement – 02 floor slab - Work in Progress - Status as of October 2020

Arcadia - Total Estimated Qty – 85,000 Cum, Excavated Qty-55,000 Cum. Retaining wall raft – 108/375 Rmt & Retaining wall – 50/375 Rmt completed. Footing Progress 15/103 Nos completed & 7/117 Nos column completed - Status as of October 2020

Tranquil - Total Estimated Qty – 1,60,000 Cum, Excavated Qty – 1,30,000 Cum. Retaining wall raft in Q tower 40/585 Rmt. Q Tower PCC 600/6217 Sqm Completed - Status as of October 2020

Tranquil - Total Estimated Qty – 1,60,000 Cum, Excavated Qty – 1,30,000 Cum. Retaining wall raft in Q tower 40/585 Rmt. Q Tower PCC 600/6217 Sqm Completed - Status as of October 2020

Serene Tower A 12th Floor slab structure works completed. Tower B 11th Floor slab structure works completed – Status as of September 2020

Serene Tower – C 10th Floor slab structure works completed. Tower – D 12th Floor slab structure works completed – Status as of September 2020

Serene Tower E 14th Floor slab structure works completed. Tower - F 14th Floor slab structure works under progress – Status as of September 2020

Serene Tower G 13th Floor slab structure works completed. Tower H 14th Floor slab structure works completed – Status as of September 2020

Serene Tower C & E Low-rise - 8th Floor structure works under progress – Status as of September 2020

Serene G & E Extension - 4th Floor structure works under progress – Status as of September 2020

Serene B05 Tower/Wing A – Casting of 12th Floor Slab was completed on September 4th 2020

Eden Tower A Completion of Fourth floor slab Milestone - Status as of September 2020

Eden - Tower A - 4th & 5th Floor structure works under progress – Status as of September 2020

Eden Tower B - 3rd Floor structure works under progress - Status as of September 2020

Eden Tower C - 10th Floor structure works under progress - Status as of September 2020

Eden Tower D - 5th Floor structure works under progress - Status as of September 2020

Eden Tower E - 9th Floor structure works under progress - Status as of September 2020

Serene Wing D - On Casting of 12th floor slab – Status as of 30th September 2020

Eden Wing E - On Casting of 8th floor slab – Status as of 30th September 2020

Eden Tower D – On Casting of Fourth floor slab - Status as of 25th September 2020

Eden Tower C - On casting of 8th floor slab - Status as of 19th September - 2020

Serene Tower G - On Casting of 12th Floor Slab - 16th September 2020

Eden B03 Tower B - On Casting of 1st Floor Slab - 16th September 2020

Serene B05 Tower/Wing F - Casting of 12th Floor Slab is completed – Status as of September 2020

Project Milestones Utopia Serene Wing C - On Casting of Eighth floor slab – Status as of September 2020

Project Milestones Utopia Serene Wing C - On Casting of Eighth floor slab - Status as of September 2020

Project Milestones Utopia Serene Wing E - On Casting of Twelfth floor slab – Status as of September 2020

Project Milestones Utopia Serene Wing E - On Casting of Twelfth floor slab - Status as of September 2020

Project Milestones Utopia Serene Wing H - On Casting of Twelfth floor slab - Status as of September 2020

Front elevation view of the Serene block – Status as of August 2020

Serene Tower - Status as of August 2020

Serene Tower A 11th floor slab in progress & Tower B 10th floor slab completed – Status as of August 2020

Serene Tower C 8th floor slab in progress & Tower D 11th floor slab in progress - Status as of August 2020

Serene Tower E 12th floor slab in progress & Tower F 12th floor slab in progress - Status as of August 2020

Serene Tower G 12th floor slab in progress & Tower H 12th floor slab in progress - Status as of August 2020

Serene Low rise between C & E - 7th Floor slab work under progress - Status as of August 2020

Serene Low rise between G & E - 3rd Floor slab work under progress - Status as of August 2020

Eden Tower A - Part of 2nd Floor slab and part of 3rd floor slab in progress - Status as of August 2020

Eden Tower B – First floor slab in progress - Status as of August 2020

Eden Tower C - Part of 7th floor & part of 8th floor slab work in progress - Status as of August 2020

Eden Tower D - 4th floor slab work under progress - Status as of August 2020

Eden Tower E – Part of 6th floor slab work and part of 7th floor slab work under progress - Status as of August 2020

Eden Wing E - On Casting of Fourth floor slab - Status as of August 11th 2020

Eden Wing B - On Casting of Ground floor slab - Status as of August 5th 2020

Eden Wing B - On Casting of Ground floor slab - Status as of August 5th 2020

Halcyon Tower I : Basement - 2 completed. Basement-1 slab work in progress - Status as of August 2020

Halcyon Tower I & J : Basement - 3 columns and Basement - 2 slabs work in progress - Status as of August 2020

Club House - Oasis Basement structure work under progress - Status as of August 2020

Club House – Oasis Basement structure work under progress - Status as of August 2020

Cineplex & Retail - Arcadia Excavation Completed. Retaining wall work in progress - Status as of August 2020

Cineplex & Retail - Arcadia Excavation Completed. Retaining wall work in progress - Status as of August 2020

Tranquil Tower K, L, M, N, O, P & Q Excavation under progress - Status as of August 2020

Serene Tower A 9th floor slab in progress & Tower B 8th floor slab completed - Status as of July 2020

Serene Tower C 6th floor slab in progress & Tower D 9th floor slab in progress - Status as of July 2020

Serene Tower E 10th floor slab in progress & Tower F 10th floor slab in progress - Status as of July 2020

Serene Tower G 11th floor slab in progress & Tower H 10th floor slab in progress - Status as of July 2020

Serene Low rise between C & E Tower - 7th Floor slab work under progress - Status as of July 2020

Serene Low rise between G & E Tower - 3rd Floor slab work under progress - Status as of July 2020

Eden Tower A - Part of 2nd Floor slab and part of 3rd floor slab in progress - Status as of July 2020

Eden Tower B - Ground floor slab in progress - Status as of July 2020

Eden Tower C - 5th floor slab work in progress - Status as of July 2020

Eden Tower D - 3rd floor slab work under progress - Status as of July 2020

Eden Tower E - Part of 4th floor slab work and part of 5th floor slab work under progress - Status as of July 2020

Halcyon Tower I & J foundation completed - Status as of July 2020

Club House – Oasis Basement structure work under progress - Status as of July 2020

Club House – Oasis Basement structure work under progress - Status as of July 2020

Cineplex & Retail - Arcadia Excavation Completed - Status as of July 2020

Cineplex & Retail - Arcadia Excavation Completed - Status as of July 2020

Tranquil Tower K, L, M, N, O, P & Q Excavation under progress - Status as of July 2020

Tranquil Tower K, L, M, N, O, P & Q Excavation under progress - Status as of July 2020

Serene – Tower B – Casting of 8th Floor Slab Completion - 30th-July-2020

Serene – Tower B – Casting of 8th Floor Slab Completion - 30th-July-2020

Serene D - On casting of 8th floor slab - Status as of 14th-July-2020

Serene D - On casting of 8th floor slab - Status as of 14th-July-2020

Serene E - Casting of Eighth floor slab complete - Status as of 06-July-2020

Halcyon - Tower I & J Upper basement structure work under progress - Status as of June 2020

Tranquil - Tower K, L, M, N, O, P & Q Excavation under progress - Status as of June 2020

Oasis Club House - Basement structure work under progress - Status as of June 2020

Arcadia Cineplex & Retail - Excavation under progress - Status as of June 2020

Serene - Tower A & B - Tower A - 9th Floor & Tower B - 7th Floor structure works under progress - Status as of June 2020

Serene - Tower C & D - Tower C - 6th Floor & Tower D - 8th Floor structure works under progress - Status as of June 2020

Serene - Tower E & F - Tower E - 8th Floor & Tower F - 10th Floor structure works under progress - Status as of June 2020

Serene - Tower G & H, 10th Floor structure works under progress - Status as of June 2020

Serene – C & E Low-rise, 7th Floor structure works under progress - Status as of June 2020

Serene – Tower G & E, 3rd Floor structure works under progress - Status as of June 2020

Eden - Tower A - Second floor structure work under progress - Status as of June 2020

Eden - Tower B - Ground floor structure work under progress - Status as of June 2020

Eden - Tower C - Fifth floor structure work under progress - Status as of June 2020

Eden - Tower D - Casting of Second floor slab completed – Status as of 04-July-2020

Halcyon - Tower I - Raft completed - Status as of May 2020

Halcyon - Tower J - Raft work under progress - Status as of May 2020

Tranquil - Excavation work in Progress - Status as of May 2020

Tranquil - Excavation work in Progress - Status as of May 2020

Serene - Tower A - 8th Floor slab Casting Completed & Tower B - 5th Floor slab structure works under progress - Status as of May 2020

Serene - Tower C - 5th Floor slab structure works under progress - Status as of May 2020

Serene - Tower D - 8th Floor slab structure works in progress - Status as of May 2020

Serene - Tower E - 7th Floor slab structure works under progress - Status as of May 2020

Serene - Tower F - 9th Floor slab structure works under progress - Status as of May 2020

Serene - Tower G - 8th Floor slab structure work in progress & Tower H - 10th Floor slab structure works under progress - Status as of May 2020

Serene - C & E Low-rise - Tower C - 6th Floor slab structure works under progress - Status as of May 2020

Serene - Tower G & E low rise - Tower G - 3rd Floor slab structure works under progress - Status as of May 2020

Eden - Tower A - Part of First floor slab and part of Second Floor slab structural work in progress - Status as of May 2020

Eden - Tower B - Upper basement slab work in progress - Status as of May 2020

Eden - Tower C - Fourth floor slab structure work in progress - Status as of May 2020

Eden - Tower D - Part of First floor slab and part of second floor slab structure work in progress - Status as of May 2020

Eden - Tower E - Part of First floor slab and part of Second Floor slab structural work in progress - Status as of May 2020

Serene – B05 Tower/Wing F – Casting of 8th Floor Slab was completed - Status as of May 2020

Oasis – Ground floor slab shuttering work in progress - Status as of March 2020

Halcyon - Foundation work of Tower I and J in progress - Status as of March 2020

Arcadia - Excavation Completed - Status as of March 2020

Tranquil - Excavation in progress - Status as of February 2020

Serene - Tower A – 8th Floor Slab Work in progress - Status as of March 2020

Serene - Tower B – 4th Floor Slab Completed & 5th Floor Slab work in progress - Status as of March 2020

Serene - Tower C – 4th Floor Slab Completed & 5th Floor Slab work in progress - Status as of March 2020

Serene - Tower D – 8th Floor Slab Work in progress - Status as of March 2020

Serene - Tower E – 6th Floor slab works under progress - Status as of March 2020

Serene - Tower F – 8th Floor slab works in progress - Status as of March 2020

Serene - Tower G – 8th Floor slab works in progress - Status as of March 2020

Serene - Tower H – 8th Floor Slab Work Completed & 9th Floor slab works in progress - Status as of March 2020

Serene - Tower C & E – 6th Floor slab works in progress - Status as of March 2020

Serene - Tower G & E – 3rd Floor slab works under progress - Status as of March 2020

Eden - Tower A - First floor slab 66% completed, Part of Second floor slab works under progress - Status as of March 2020

Eden - Tower B - Upper Basement slab work in progress - Status as of March 2020

Eden - Tower C - Third floor slab completed - Status as of March 2020

Eden - Tower D - Second floor slab 50% completed - Status as of March 2020

Eden - Tower E - First floor slab 50% completed, Second floor slab work under progress - Status as of March 2020

Oasis – Oasis – Excavation Completed , 38/51 Footing, 36/69 Columns upto UBL & 122 Rmt / 247 Rmt Retaining wall completed - under progress - Status as of February 2020

Halcyon - Excavation completed , 56/191 Footings, 12/245 Column upto UBL & Retaining wall raft 232/547 Rmt, Wall 179/547 Rmt completed - under progress - Status as of February 2020

Arcadia - Excavation Under Progress - 44,000 out of 80,000 Cum completed, PCC started on 26th Feb’20 - under progress - Status as of February 2020

Tranquil - Excavation Under Progress – 10,000 out of 1,60,000 Cum completed - under progress - Status as of February 2020

Serene - Tower A & B - Tower A – Gf to 5th Floor structure works Completed, 6th Floor, Tower B – GF to 4th Floor structure works Completed, 5th Floor under progress - Status as of February 2020

Serene - Tower C & D - Tower D – Gf to 6th Floor structure works Completed, 7th Floor, Tower C – GF to 4th Floor structure works Completed, 5th Floor under progress - Status as of February 2020

Serene - Tower C & E - GF to 3rd Floor structure works completed, 4th Floor - under progress - Status as of February 2020

Serene - Tower E & F - Tower F – Gf to 6th Floor structure works Completed, 7th Floor, Tower E – GF to 5th Floor structure works Completed, 6th Floor - under progress - Status as of February 2020

Serene - Tower G & H - Tower H – Gf to 7th Floor structure works Completed, 8th Floor, Tower G– GF to 5th Floor structure works Completed, 6th Floor - under progress - Status as of February 2020

Serene - Tower E & G - GF to 1st Floor structure works completed, 2nd Floor - under progress - Status as of February 2020

Eden - Tower A - Upper basement slab Completed - 100, GF Slab 100% completed, 1st Floor floor slab – under progress - Status as of February 2020

Eden - Tower B - Footing Completed , STP Wall casted, UBL floor slab pour 1 casted – under progress - Status as of February 2020

Eden - Tower C - GF to 1st Floor structure works completed, 2nd Floor – under progress - Status as of February 2020

Eden - Tower D - GF to 1st Floor structure works completed, 2nd Floor – under progress - Status as of February 2020

Eden - Tower E - GF to 1st Floor structure works – under progress - Status as of February 2020

Oasis – Excavation Completed , 33/51 Footing & 34 Rmt / 247 Rmt Retaining wall completed - Status as of February 2020

Halcyon - Excavation completed , 11/188 Footing & Retaining wall raft 196/507 Rmt completed - Status as of January 31st 2020

Arcadia - Excavation Under Progress - 30,000 out of 80,000 Cum completed - Status as of January 31st 2020

Serene - Tower A & B - Footing, Back Filling, Grade Slab, Columns till Ground floor completed, Ground floor slab for Tower Completed, Tower A – Gf to 3rd Floor Completed, 4th Floor 2/6 Flats completed, Tower B – GF to 2nd Floor Completed, 3rd Floor under progress - Status as of January 31st 2020

Serene - Tower C & D - Footing, Back Filling, Grade Slab, Columns till Ground floor completed, Ground floor slab for Tower Completed,Tower D – Gf to 4th Floor Completed, 5th Floor under progress, Tower C – GF to 2nd Floor Completed, 3rd Floor under progress - Status as of January 31st 2020

Serene - Tower C & E - Footing Completed, Back Filling, Grade Slab, Columns till Upper Basement completed, upper basement floor slab completed, GF slab Completed GF to 1st Floor 5/5 Flats completed, 2nd Floor under progress - Status as of January 31st 2020

Serene - Tower E & F - Footing, Back Filling, Grade Slab, Columns till Ground floor completed, Ground floor slab for Tower Completed, Tower F – Gf to 4th Floor Completed, 5th Floor 2/6 Flats completed, Tower E – GF to 2nd Floor Completed, 3rd Floor under progress - Status as of January 31st 2020

Serene - Tower G & H - Footing, Back Filling, Grade Slab, Columns till Ground floor completed, Ground floor slab for Tower Completed, Tower H – Gf to 5th Floor Completed, 6th Floor under progress, Tower G– GF to 3rd Floor Completed, 4th Floor under progress - Status as of January 31st 2020

Serene - Tower G & E - Footing Completed, Back Filling, Grade Slab, Columns till Upper Basement completed, upper basement completed.GF Slab Completed, 1st Floor under progress - Status as of January 31st 2020

Eden - Tower A - Footing, backfilling, grade slab completed, columns till upper basement completed, upper basement slab Completed -75% , GF Slab 40% completed - Status as of January 31st 2020

Eden - Tower B - Mass Excavation completed, Footing Completed , STP Walls on Progress - Status as of January 31st 2020

Eden - Tower C - Footings completed, columns till upper basement completed, UB Slab –Complete, GF Completed, 1st Floor Slab Pour-1 completed - Status as of January 31st 2020

Eden - Tower D - Footing, backfilling, grade slab completed, columns till upper basement completed, upper basement slab Completed, GF Slab Completed,1st Floor pour-1 completed - Status as of January 31st 2020

Eden - Tower E - Footing, backfilling, grade slab completed, columns till upper basement completed, Back filling Completed, UG Sump Raft Completed, UG Sump Walls & Slab Completed -90% for Upper Basement - Status as of January 31st 2020

Eden - Retaining Wall - 528/ 574 Rmt Retaining wall completed upto Upper Basement level, 119/574 Rmt Retaining wall completed upto GF level - Status as of January 31st 2020

Oasis – Excavation Completed , 22/49 Footing & 34 Rmt / 247 Rmt Retaining wall completed - Status as of December 31st 2019

Halcyon - Excavation 55,000 Cum out of 70,000 Cum , P.C.C for Retaining Wall Started - Status as of December 31st 2019

Arcadia - Excavation Under Progress -15,000 out of 80,000 Cum - Status as of December 31st 2019

Serene - Tower A & B - Footing, Back Filling, Grade Slab, Columns till Ground floor completed, Ground floor slab for Tower Completed, Tower A – Gf to 1st Floor – Completed, 2nd Floor Completed, 3rd Floor 2/6 Flats Completed, Tower B – GF to 1st Floor Completed, 2nd Floor under Progress - Status as of December 31st 2019

Serene - Tower C & D - Footing, Back Filling, Grade Slab, Columns till Ground floor completed, Ground floor slab for Tower Completed, Tower D – Gf to 1st Floor – Completed, 2nd Floor Completed, 3rd Floor 2/6 Flats Completed, Tower C – GF to 1st Floor Completed, 2nd Floor under Progress - Status as of December 31st 2019

Serene - Tower E & F - Footing, Back Filling, Grade Slab, Columns till Ground floor completed, Ground floor slab for Tower Completed, Tower F – Gf to 1st Floor – Completed, 2nd Floor Completed , 3rd floor Completed , 4th Floor Under Progress, Tower E – GF to 1st Floor Completed, 2nd Floor under Progress - Status as of December 31st 2019

Serene - Tower G & H - Footing, Back Filling, Grade Slab, Columns till Ground floor completed, Ground floor slab for Tower Completed, Tower H – Gf to 1st Floor – Completed, 2nd Floor Completed , 3rd floor Completed , 4th Floor Under Progress, Tower G– GF to 1st Floor Completed, 2nd Floor under Progress - Status as of December 31st 2019

Serene - Tower C & E - Footing Completed, Back Filling, Grade Slab, Columns till Upper Basement completed, upper basement floor slab completed, GF slab Completed, GF to 1st Floor Under Progress (S-form) - Status as of December 31st 2019

Serene - Tower G & E - Footing Completed, Back Filling, Grade Slab, Columns till Upper Basement completed, upper basement completed.GF Slab under Progress - Status as of December 31st 2019

Eden - Tower A - Footing, backfilling, grade slab completed, columns till upper basement completed, upper basement slab Completed -75% , GF Slab Under Progress - Status as of December 31st 2019

Eden - Tower B - Mass Excavation completed, Footing Completed , STP Walls on Progress - Status as of December 31st 2019

Eden - Tower C - Footings completed, columns till upper basement completed, UB Slab –Complete, GF Completed, 1st Floor Slab Under Progress (S-form) - Status as of December 31st 2019

Eden - Tower C - Footing, backfilling, grade slab completed, columns till upper basement completed, upper basement slab Completed, GF Slab Completed,1st Floor Under Progress - Status as of December 31st 2019

Eden - Tower D - Footing, backfilling, grade slab completed, columns till upper basement completed, upper basement slab Completed, GF Slab Completed,1st Floor Under Progress - Status as of December 31st 2019

Eden - Tower E - Footing, backfilling, grade slab completed, columns till upper basement completed, Back filling Completed, UG Sump Raft Completed, UG Sump Walls & Slab Completed -60% for Upper Basement - Status as of December 31st 2019

Halcyon - Excavation under Progress – 44000/ 70000 Cum Completed , Civil Work yet to start

Serene - Tower A & B - Footing, Back Filling, Grade Slab, Columns till Ground floor completed Ground floor slab for Tower Completed, Tower A – Gf to 1st Floor – Completed, 2nd Floor Under progress, Tower B – GF to 1st Floor Under Progress - Status as of December 2019

Serene - Tower C & D - Footing, Back Filling, Grade Slab, Columns till Ground floor completed Ground floor slab for Tower Completed, Tower A – Gf to 1st Floor – Completed, 2nd Floor Under progress, Tower B – GF to 1st Floor Under Progress - Status as of December 2019

Serene - Tower E & F - Footing, Back Filling, Grade Slab, Columns till Ground floor completed, Ground floor slab for Tower Completed, Tower F – Gf to 1st Floor – Completed, 2nd Floor Completed , 3rd floor Under Progress (S-form), Tower E – GF to 1st Floor Under Progress (S-form) - Status as of December 2019

Serene - Tower G & H - Footing, Back Filling, Grade Slab, Columns till Ground floor completed, Ground floor slab for Tower Completed, Tower H – Gf to 1st Floor – Completed, 2nd Floor Completed , 3rd floor Under Progress (S-form), Tower G– GF to 1st Floor Under Progress (S-form) - Status as of December 2019

Eden - Tower A - 23/26 Footings completed, 42/65 Nos Columns Completed, Upper Basement 30% Completed, Balance Slab & Lift Area under Progress - Status as of December 2019

Eden - Tower D - Footing, backfilling, grade slab completed, columns till upper basement completed, upper basement slab Completed, GF 50% Slab Completed, Balance 50% Under Progress

Eden - Tower D - Footing, backfilling, grade slab completed, columns till upper basement completed, upper basement slab Completed, GF 50% Slab Completed, Balance 50% Under Progress - Status as of December 2019

Eden - Tower E - Footing, backfilling, grade slab completed, columns till upper basement completed, slab formwork under progress for UB level, Back filling Completed, UG Sump Raft Completed, UG Sump Walls Under Progress - Status as of December 2019

Serene - Tower A & B - Ground floor slab Completed - Status as of November 2019

Serene - Tower C & D - Upper basement floor slab completed for Tower C and Ground Floor slab completed for Tower D - Status as of November 2019

Serene - Tower E & F - Ground Floor Slab completed - Status as of November 2019

Serene - Tower G & H - Ground Floor Slab completed, 1st floor slab in progress - Status as of November 2019

Eden - Tower D - Raft completed - Status as of November 2019

Eden - Tower E - Raft under progress - Status as of November 2019

Eden - Tower A - Raft under progress - Status as of November 2019

Eden - Tower C - Raft under progress - Status as of November 2019

Serene - Tower A & B - Raft & Upper basement floor slab completed, Ground floor slab in Progress - Status as of October 2019

Serene - Tower C & D - Raft & Upper basement floor slab completed, Ground floor slab in Progress - Status as of October 2019

Serene - Tower E & F - Tower – E- Raft & Upper basement floor slab completed, Ground floor slab in Progress Tower – F - Raft & Upper basement floor slab completed, Ground floor slab completed - Status as of October 2019

Serene - Tower G & H - Raft & Upper basement floor slab, Ground floor slab completed and First floor slab is in Progress - Status as of October 2019

Eden - Tower D - Raft completed , upper basement slab in progress - Status as of October 2019

Eden - Tower E - Raft in progress - Status as of October 2019

Eden - Tower A - Raft in progress - Status as of October 2019

Eden - Tower C - Raft in progress - Status as of October 2019

Serene - Tower A & B - Upper Basement Slab casted for both the towers - Status as of August 2019

Serene - Tower C & D - Upper Basement Slab casted for both the towers - Status as of August 2019

Serene - Tower E & F - Upper Basement Slab casted for both the towers - Status as of August 2019

Serene - Tower G & H - Tower H Upper Basement Slab casted - Tower G Ground floor Slab Completed - Status as of August 2019

Eden - Tower A - Mass excavation completed. PCC works in progress - Status as of August 2019

Eden - Tower B - Excavation in progress - Status as of August 2019

Eden - Tower C - Footings and Column works for Lower Basement in progress - Status as of August 2019

Eden - Tower D - Footings and Column works for Lower Basement in progress - Status as of August 2019

Eden - Tower E - Footings and Column works for Lower Basement in progress - Status as of August 2019

Eden - D Block - Status as of August 2019

Eden - E Block - Status as of August 2019

Serene - A & B Block - Status as of August 2019

Serene - C & D Block - Status as of August 2019

Serene - E & F Block - Status as of August 2019

Serene - E & F_1 - Status as of August 2019

Serene - G & H _1 Block - Status as of August 2019

Serene - G & H Block - Status as of August 2019

Serene - R1 Block - Status as of August 2019

Serene - R2 Block - Status as of August 2019

Serene - R2_1 Block - Status as of August 2019

Serene - R3 Block - Status as of August 2019

A & B PCC of 300 Sqm staging is in progress - Status as of July 2019

Tower C & D PCC of 150 Sqm ready to take up form work - Status as of July 2019

E & F PCC 100 Sqm completed and staging work started - Status as of July 2019

G & H – Tower G slab is ready for concreting by 5th July 19 Tower H back filling 95 % completed and PCC of 330 Sqm completed and staging work started - Status as of July 2019

Serene North west corner progress - Status as of July 2019

Ribbon-01 – out of 33 footing 4 is completed 40% PCC completed - Status as of July 2019

Ribbon-02 out of 46 - 6 footing ready for concreting - Status as of July 2019

Ribbon-03 in 29 footing 15 footing and 4 column completed - Status as of July 2019

Tower G slab curing work progress - Status as of July 2019

Tower G from B1 to Podium column progress - Status as of July 2019

Eden Tower D & E PCC for footing 800 Sqm and 10 no footing concrete completed - Status as of July 2019

Eden Tower D & E PCC for footing 800 Sqm and 10 no footing concrete completed - Status as of July 2019



© Brigade Cornerstone Utopia - 2020  |  About Brigade  |  Disclaimer

Enquire Now

Speak to us

Please select your country and enter your phone number

I Agree to the Terms & Conditions

Please wait..

Thank you for requesting a call back
Our team will get back to you shortly!