Status

Eden Tower A : Completion of 24th floor slab Milestone – Status as of 14th September 2021

Paradise Tower F : Casting of Raft/Footing Milestone – Status as of September 9th 2021

Eden Tower C : Completion of Terrace floor slab Milestone – Status as of 9th September 2021

Tranquil Tower P : Ground Floor slab - Casted on 5th September 2021

Serene View From East side : Ribbon 3 – 7th Floor slab structure works in progress – Status as of August 2021

Serene View from westside - Status as of August 2021

Serene : Flooring in progress in all towers - Status as of August 2021

Eden Tower A : 23rd & 25th Floor structure works in progress. Eden Tower C : Terrace Floor structure works in progress. Other Towers Terrace Floor structure works completed – Status as of August 2021

Eden Tower A,Tower C, Tower E : Flooring – Status as of August 2021

Eden Tower A, Tower C, Tower E : Painting – Status as of August 2021

Halcyon : Overall view. Halcyon Tower I – 17th Floor structure works in progress. Halcyon Tower J – 7th Floor structure works in progress – Status as of August 2021

Oasis : Fourth floor structure works in progress. Swimming pool foundation works in progress – Status as of August 2021

Arcadia : First floor slab in progress – Status as of August 2021

Tranquil Tower K : First Floor structure works in progress. Tranquil Tower L : Second Floor structure works in progress. Tranquil Tower M : First Floor structure works in progress. Tranquil Tower N : GF & FF structure works in progress. Tranquil Tower O : GF structure works in progress. Tranquil Tower P : GF structure works in progress. Tranquil Tower Q : FF structure works in progress – Status as of August 2021

Paradise Tower F : B1 level Slab decking in progress – Status as of August 2021

Paradise Tower H : Raft/Footing work in progress – Status as of August 2021

Paradise Tower J : Excavation Wok in Progress – Status as of August 2021

Paradise Tower L : B1 Slab in Progress – Status as of August 2021

Eden Tower A : North Elevation – Status as of August 2021

Eden Tower B : East & West Elevation – Status as of August 2021

Eden Tower C : North Elevation – Status as of August 2021

Eden Tower D : West Elevation – Status as of August 2021

Eden Tower D : Swimming pool work in progress – Status as of August 2021

Eden Tower E : North Elevation – Status as of August 2021

Eden Tower B : Completion of 8th floor slab – Status as of 28th August 2021

Halcyon Tower I : Casting of 16th floor Slab – Status as of 26th August 2021

Brigade Cornerstone Utopia Serene Tower/Wing D : Casting of Terrace Floor Slab – Status as of 21st August 2021

Serene Tower E : Commencement of Painting – Status as of 17th August 2021

Serene Tower E : Commencement of Painting – Status as of 17th August 2021

Serene Tower E : Commencement of Painting – Status as of 17th August 2021

Serene Tower F : Commencement of Painting – Status as of 17th August 2021

Serene Tower F : Commencement of Painting – Status as of 17th August 2021

Serene Tower F : Commencement of Painting – Status as of 17th August 2021

Brigade Cornerstone Utopia Serene Tower/Wing C : Casting of Terrace Floor Slab - Status as of 9th August 2021

Brigade Cornerstone Utopia Serene Tower/Wing A : Casting of Terrace Floor Slab - Status as of 9th August 2021

Tranquil Tower O : Casting of Upper basement floor slab – Status as of 5th August 2021

Serene B : On commencement of Painting - Status as of 3rd August 2021

Serene B : On commencement of Painting - Status as of 3rd August 2021

Serene B : On commencement of Painting - Status as of 3rd August 2021

Serene B : On commencement of Painting - Status as of 3rd August 2021

Serene B : On commencement of Painting - Status as of 3rd August 2021

Serene C : On commencement of Painting – Status as of 3rd August 2021

Serene C : On commencement of Painting – Status as of 3rd August 2021

Serene C : On commencement of Painting – Status as of 3rd August 2021

Serene C : On commencement of Painting – Status as of 3rd August 2021

Eden Tower A : Completion of 20th floor slab Milestone - Status as of 2nd August 2021

Serene Tower A : Terrace Floor slab structure works in progress – Status as of July 2021

Serene Tower B : Above Terrace structure works in progress - Status as of July 2021

Serene Tower C : Terrace floor slab structure works in progress - Status as of July 2021

Serene Tower D : Terrace Floor slab structure works in progress - Status as of July 2021

Serene Tower E : Above Terrace structure works in progress - Status as of July 2021

Serene Tower F : Above Terrace structure works in progress - Status as of July 2021

Serene Tower G : Above Terrace structure works in progress - Status as of July 2021

Serene Tower H : Above Terrace structure works in progress - Status as of July 2021

Serene Tower C – E Low-rise : Above Terrace structure works in progress - Status as of July 2021

Serene Tower E – G Low-rise : Above Terrace structure works in progress - Status as of July 2021

Serene Tower B – C Low-rise : 6th floor slab structure works in progress - Status as of July 2021

Serene Flooring in progress in all towers - Status as of July 2021

Serene Painting in progress in Towers A, D, G & H - Status as of July 2021

Eden Overall view – Status as of July 2021

Eden Tower A : Part 21st & 22nd Floor structure works in progress – Status as of July 2021

Eden Tower B : Terrace Floor structure work in progress – Status as of July 2021

Eden Tower C : 25th Floor structure works in progress – Status as of July 2021

Eden Tower D : Above terrace works in progress – Status as of July 2021

Eden Tower E : Terrace floor structure works completed. Above terrace works in progress – Status as of July 2021

Eden Tower A, Tower C, Tower E : Flooring – Status as of July 2021

Eden Tower A, Tower C, Tower E : Painting – Status as of July 2021

Halcyon Overall view – Status as of July 2021

Halcyon Tower I : 14th Floor structure works in progress - Status as of July 2021

Halcyon Tower J : 5th Floor structure work in progress - Status as of July 2021

Oasis Clubhouse : 3rd floor structure works in progress - Status as of July 2021

Arcadia : Podium part Upper basement slab & Ground floor slab in progress - Status as of July 2021

Paradise Tower F : Foundation, columns and retaining wall works in progress - Status as of July 2021

Paradise Tower L : Upper basement slab structure works in progress. Paradise Tower J & K : Retaining wall works in progress - Status as of July 2021

Elysium : Footings, UG sump and STP works in progress - Status as of July 2021

Tranquil Overall view - Status as of July 2021

Tranquil Tower K : Ground Floor structure completed - Status as of July 2021

Tranquil Tower L : First Floor structure works in progress - Status as of July 2021

Tranquil Tower M : Tower area ground floor slab structure works completed. Low rise Tower M-N ground floor slab structure works in progress - Status as of July 2021

Tranquil Tower N : First floor structure works in progress - Status as of July 2021

Tranquil Tower O : Upper Basement slab structure works in progress - Status as of July 2021

Tranquil Tower P : Ground floor slab structure works in progress - Status as of July 2021

Tranquil Tower Q : Ground Floor slab structure works completed - Status as of July 2021

Eden Tower C : Completion of 24th floor slab Milestone - Status as of 30th July 2021

Eden Tower A : commencement of Painting milestone - Status as of 30th July 2021

Eden Tower A : commencement of Painting milestone - Status as of 30th July 2021

Eden Tower A : commencement of Painting milestone - Status as of 30th July 2021

Eden Tower A : commencement of Painting milestone - Status as of 30th July 2021

Eden Tower A : commencement of Painting milestone - Status as of 30th July 2021

Eden Tower B : Completion of 7th floor slab Milestone – Status as of 22nd July 2021

Eden Tower E : On Casting of Terrace slab - Status as of 19th July 2021

Tranquil Building - Tower P - Casting of Upper Basement slab – Status as of 19th July 2021

Halcyon : On Casting of 4th floor Slab Tower J – Status as of 15th July 2021

Halcyon : Casting of 12th floor Slab Tower I – Status as of 10th July 2021

Brigade Cornerstone Utopia : SERENE Tower/Wing D – Commencement of Painting – Status as of 8th July 2021

Brigade Cornerstone Utopia : SERENE Tower/Wing D – Commencement of Painting – Status as of 8th July 2021

Brigade Cornerstone Utopia : SERENE Tower/Wing D – Commencement of Painting – Status as of 8th July 2021

Brigade Cornerstone Utopia : SERENE Tower/Wing D – Commencement of Painting – Status as of 8th July 2021

Brigade Cornerstone Utopia : SERENE Tower/Wing A – Commencement of Painting – Status as of 8th July 2021

Brigade Cornerstone Utopia : SERENE Tower/Wing A – Commencement of Painting – Status as of 8th July 2021

Brigade Cornerstone Utopia : SERENE Tower/Wing A – Commencement of Painting – Status as of 8th July 2021

Brigade Cornerstone Utopia : SERENE Tower/Wing A – Commencement of Painting – Status as of 8th July 2021

Brigade Cornerstone Utopia : SERENE Tower/Wing G – Commencement of Painting - Status as of 8th July 2021

Brigade Cornerstone Utopia : SERENE Tower/Wing G – Commencement of Painting - Status as of 8th July 2021

Brigade Cornerstone Utopia : SERENE Tower/Wing G – Commencement of Painting - Status as of 8th July 2021

Brigade Cornerstone Utopia : SERENE Tower/Wing G – Commencement of Painting - Status as of 8th July 2021

Brigade Cornerstone Utopia : SERENE Tower/Wing H – Commencement of Painting - Status as of 8th July 2021

Brigade Cornerstone Utopia : SERENE Tower/Wing H – Commencement of Painting - Status as of 8th July 2021

Brigade Cornerstone Utopia : SERENE Tower/Wing H – Commencement of Painting - Status as of 8th July 2021

Brigade Cornerstone Utopia : SERENE Tower/Wing H – Commencement of Painting - Status as of 8th July 2021

Serene Tower/Wing B : Casting of Terrace Floor Slab – Status as of 8th July 2021

Serene Tower/Wing B : Casting of Terrace Floor Slab – Status as of 8th July 2021

Tranquil Tower/Wing M : Casting of Ground Floor Slab - Status as of 6th July 2021

Paradise Tower L : Completion of Raft/Footings Milestone - Status as of 2nd July 2021

Serene Tower A : 26th Floor slab structure works in progress – Status as of June 2021

Serene Tower B : Terrace Floor slab structure works in progress - Status as of June 2021

Serene Tower C : 25th Floor slab structure works in progress - Status as of June 2021

Serene Tower D : 25th Floor slab structure works in progress - Status as of June 2021

Serene Tower E : Above Terrace structure works in progress - Status as of June 2021

Serene Tower F : Above Terrace structure works in progress - Status as of June 2021

Serene Tower G : Above Terrace structure works in progress - Status as of June 2021

Serene Tower H : Above Terrace structure works in progress - Status as of June 2021

Serene Tower C – E Low-rise : Above Terrace structure works in progress Status as of June 2021

Serene Tower E – G Low-rise : Above Terrace structure works in progress - Status as of June 2021

Serene Tower B – C Low-rise : Fourth floor slab structure works in progress - Status as of June 2021

Serene Flooring - Tower A, Tower C, Tower E, Tower G, Tower E-G - Status as of June 2021

Eden Overall view – Status as of June 2021

Eden Tower A : Part 20th & 18th Floor structure works in progress – Status as of June 2021

Eden Tower B : 7th Floor structure work in progress – Status as of June 2021

Eden Tower C : Part Terrace & 23rd Floor structure works in progress – Status as of June 2021

Eden Tower D : Terrace Floor structure completed. Above terrace works in progress – Status as of June 2021

Eden Tower E : Terrace floor structure works in progress – Status as of June 2021

Eden Tower A, Tower C, Tower E : Flooring – Status as of June 2021

Oasis Clubhouse : Part 2nd floor & 3rd floor structure works in progress - Status as of June 2021

Arcadia : Podium part Upper basement slab & Ground floor slab in progress - Status as of June 2021

Paradise Tower F : Foundation and retaining wall works in progress - Status as of June 2021

Paradise Tower L : Foundation works in progress. Tower J & K : Retaining wall works in progress - Status as of June 2021

Elysium : Footings, UG sump and STP works in progress - Status as of June 2021

Tranquil Overall view - Status as of June 2021

Tranquil Tower K & L : Ground Floor structure completed - Status as of June 2021

Tranquil Tower M : Ground Floor slab structure works in progress - Status as of June 2021

Tranquil Tower N : Ground Floor slab structure works completed - Status as of June 2021

Tranquil Tower O : Upper Basement slab structure works in progress. Tranquil Tower P : Upper Basement slab structure works in progress - Status as of June 2021

Tranquil Tower Q : Ground Floor slab structure works completed - Status as of June 2021

Eden Tower D : Completion of 8th floor slab Milestone – Status as of 24th June 2021

Eden Tower B : Completion of 6th floor slab Milestone – Status as of 21st June 2021

Serene Tower/Wing C : On Casting of 24th Floor Slab – Status as of 18th June 2021

Serene Tower/Wing D : On Casting of 24th Floor Slab – Status as of 15th June 2021

Eden Tower C : Completion of 20th floor slab Milestone - Status as of 7th June 2021

Eden Tower A : Completion of 16th floor slab Milestone - Status as of 7th June 2021

Eden Tower C Block : Commencement of painting – Status as of May 27th 2021

Eden Tower C Block : Commencement of painting – Status as of May 27th 2021

Eden Tower C Block : Commencement of painting – Status as of May 27th 2021

Eden Tower C Block : Commencement of painting – Status as of May 27th 2021

Eden Tower E Block : Commencement of painting – Status as of May 27th 2021

Eden Tower E Block : Commencement of painting – Status as of May 27th 2021

Eden Tower E Block : Commencement of painting – Status as of May 27th 2021

Serene Tower progress – Status as of May 2021

Serene Tower A : 25th Floor slab structure works in progress. Serene Tower B : Terrace Floor slab structure works in progress – Status as of May 2021

Serene Tower C : 23rd Floor slab structure works in progress. Serene Tower D : 24th Floor slab structure works in progress progress – Status as of May 2021

Serene Tower E : Above Terrace structure works in progress. Serene Tower F : Above Terrace structure works in progress progress – Status as of May 2021

Serene Tower G : Above Terrace structure works in progress. Serene Tower H : Above Terrace structure works in progress progress – Status as of May 2021

Serene Tower C - E Low-rise : Above Terrace structure works in progress progress – Status as of May 2021

Serene Tower E & G Low-rise : Above Terrace structure works in progress progress – Status as of May 2021

Serene Tower B & C Low-rise : Third floor slab structure works in progress progress – Status as of May 2021

Eden Towers - Status as of May 2021

Eden Tower A : Part 16th & 18th Floor structure works in progress - Status as of May 2021

Eden Tower B : Part 6th Floor structure work in progress - Status as of May 2021

Eden Tower C : Part 20th & 25th Floor structure works in progress - Status as of May 2021

Eden Tower D : Part Terrace Floor structure works in progress - Status as of May 2021

Eden Tower E : 26th floor structure works in progress - Status as of May 2021

Oasis Clubhouse : Second floor structure works in progress – Status as of May 2021

Halcyon Tower I : 9th floor slab structure work in progress & Halcyon Tower J : 3rd floor slab structure work in progress - Status as of May 2021

Arcadia : Footings in podium area in progress. Podium part Upper basement slab & Ground floor slab in progress - Status as of May 2021

Tower K : GF slab completed; Tower L : GF slab completed. Tower M : UBL structure works in progress; Tower N : GF slab completed. Tower O : UBL structure works in progress; Tower P : UBL structure works in progress. Tower Q : GF structure works in progress - Status as of May 2021

Paradise Tower L : Foundation works in progress. Paradise Tower J & K : Retaining wall works in progress - Status as of May 2021

Elysium : STP works in progress - Status as of May 2021

Elysium : UG Sump Raft progress - Status as of May 2021

Tranquil Building Tower N : On Casting of Ground Floor Slab – Status as of May 31st 2021

Eden Tower C and E Block : Commencement of painting – Status as of May 27th 2021

Eden Tower C and E Block : Commencement of painting – Status as of May 27th 2021

Eden Tower D : Completion of 7th floor slab Milestone – Status as of May 19th 2021

Serene Tower/Wing A : On Casting of 24th Floor – Status as of 19th May 2021

Serene Tower/Wing A : On Casting of 24th Floor – Status as of 19th May 2021

Halcyon : On casting of 8th floor Slab - Tower I completed – Status as of 19th May 2021

Eden Tower E : On Completion of 24th floor slab - Status as of 6th May 2021

Tranquil Tower O : On Casting of Footing – Status as of May 4th 2021

Tranquil Tower O : On Casting of Footing – Status as of May 4th 2021

Serene Tower – Status as of April 2021

Serene Tower A : 24th Floor slab structure works in progress. Serene Tower B : 25th Floor slab structure works in progress – Status as of April 2021

Serene Tower : C 21st Floor slab structure works in progress. Serene Tower : D 22nd Floor slab structure works in progress – Status as of April 2021

Serene Tower E : Above Terrace structure works in progress & Serene Tower F : Above Terrace structure works in progress – Status as of April 2021

Serene Tower G : Above Terrace structure works in progress. Serene Tower H : Above Terrace structure works in progress – Status as of April 2021

Serene Tower C & E Low-rise : Above Terrace structure works in progress – Status as of April 2021

Serene Tower E & G Low-rise : Above Terrace structure works in progress – Status as of April 2021

Serene Tower B & C Low-rise : Third floor slab structure works in progress – Status as of April 2021

Eden Tower – Status as of April 2021

Eden Tower A : Part 13th, 17th & 18th Floor structure works in progress – Status as of April 2021

Eden Tower B : Part 6th Floor structure work in progress – Status as of April 2021

Eden Tower C : Part 17th & 23rd Floor structure works in progress – Status as of April 2021

Eden Tower D : Part 7th & 8th Floor structure works in progress – Status as of April 2021

Eden Tower E : 23rd & 24th floor structure works in progress – Status as of April 2021

Oasis Clubhouse : second floor structure works in progress – Status as of April 2021

Halcyon Tower I : 7th floor slab structure work in progress & Halcyon Tower J : 1st floor slab structure work in progress - Status as of April 2021

Arcadia : Footings in podium area in progress. Podium part Upper basement slab & Ground floor slab in progress – Status as of April 2021

Tranquil Tower K : GF structure works in progress. Tranquil Tower L : GF structure works in progress. Tranquil Tower M : UBL structure works in progress. Tranquil Tower N : GF structure works in progress. Tranquil Tower O : Foundation works in progress. Tranquil Tower P : Foundation works in progress. Tranquil Tower Q : GF structure works in progress – Status as of April 2021

Paradise Tower L : Foundation works in progress – Status as of April 2021

Paradise Tower L : Foundation works in progress – Status as of April 2021

Elysium Foundation works in progress – Status as of April 2021

Elysium Foundation works in progress – Status as of April 2021

Serene B : On Casting of 24th Floor Slab - Status as of 22nd April 2021

Serene B : On Casting of 24th Floor Slab - Status as of 22nd April 2021

Serene C – On Casting of 20th Floor Slab - Status as of 15th April 2021

Serene C : On Casting of 20th Floor Slab - Status as of 15th April 2020

Serene F : On Casting of Terrace Floor Slab - Status as of 15th April 2020

Tranquil Building Tower N : On Casting of Upper Basement slab – Status as of 11th April 2021

Eden Tower A : On Completion of Twelfth floor slab Milestone completed – Status as of 10th April 2021

Serene G : On Casting of Terrace Floor Slab – Status as on 8th April 2021

Eden Tower C : Completion of Sixteenth floor slab Milestone – Status as of 6th April 2021

Serene Tower E : On Casting of terrace floor slab – Status as of 5th April 2021

Eden Tower D : On Completion of Sixth floor slab Milestone - Status as of 3rd April 2021

Serene Tower H : On Casting of Terrace Floor Slab – Status as of 31st March 2021

Serene Tower H : On Casting of Terrace Floor Slab – Status as of 31st March 2021

Serene Tower A : 22nd Floor slab structure works in progress. And Serene Tower B : 23rd Floor slab structure works in progress – Status as of March 2021

Serene Tower : C 20th Floor slab structure works in progress. And Serene Tower : D 21st Floor slab structure works in progress – Status as of March 2021

Serene Tower E : Terrace slab structure works in progress. And Serene Tower F : Terrace slab structure works in progress – Status as of March 2021

Serene Tower G : Terrace slab structure works in progress. And Serene Tower H : Terrace slab structure works completed – Status as of March 2021

Serene C – E Low-rise : Terrace slab completed – Status as of March 2021

Serene Tower E – G Low-rise : Terrace Floor slab completed – Status as of March 2021

Serene Tower B – C Low-rise : Second floor slab structure works in progress – Status as of March 2021

Serene All Towers : Flooring commenced - Status as of March 2021

Eden Tower A : Part 10th, 14th & 18th Floor structure works in progress – Status as of March 2021

Eden Tower B : Part 5th Floor structure work in progress - Status as of March 2021

Eden Tower C : Part 16th & 22nd Floor structure works in progress - Status as of March 2021

Eden Tower D : Part 6th & 7th Floor structure works in progress - Status as of March 2021

Eden Tower E : 22nd floor structure works in progress - Status as of March 2021

Eden Towers A, C & E : Flooring Commenced - Status as of March 2021

Oasis : Part First floor & Part second floor structure works in progress – Status as of March 2021

Halcyon Tower I : Fifth floor slab structure work in progress & Halcyon Tower J : First floor slab structure work in progress progress – Status as of March 2021

Arcadia : Footings in podium area in progress Podium part Upper basement slab & Ground floor slab in progress progress – Status as of March 2021

Tranquil : Footings for Tower O in progress. Footings in Towers Q, K, L ,M , N & P are completed. Upper Basement slab in Towers N in progress. Tranquil Towers Q, K, L & M completed. Ground floor slab in Tower Q & K in progress – Status as of March 2021

Tranquil Tower P : On Casting of Footings – Status as of 31st March 2021

Halcyon Tower I : On Casting of Fourth floor slab - Status as of 25th March 2021

Halcyon Tower J : On casting of Ground floor Slab - 18th March 2021

Serene Tower/Wing D : On Casting of 20th Floor Slab - 17th March 2021

Eden Tower E : Completion of 20th floor slab Milestone - Status as of 17th March 2021

Tranquil Tower Q : On Casting of Upper basement floor slab - Status as of 15th March 2021

Tranquil Tower L : On Casting of Upper Basement slab - 12th March 2021

Tranquil Tower L : On Casting of Upper Basement slab - 12th March 2021

Tranquil Tower M : On Casting of Upper Basement Slab - 12th March 2021

Tranquil Tower M : On Casting of Upper Basement Slab - 12th March 2021

Serene Tower A : 21st Floor slab structure works in progress. Serene Tower B : 21st Floor slab structure works in progress – Status as of February 2021

Serene Tower : C 17th Floor slab completed. Serene Tower : D 20th Floor slab structure works in progress – Status as of February 2021

Serene Tower E : 25th Floor slab structure works in progress. Serene Tower F : 25th Floor slab structure works in progress – Status as of February 2021

Serene Tower G : 25th Floor slab structure works in progress. Serene Tower H : 25th Floor slab structure works in progress – Status as of February 2021

Serene Tower C - E Low-rise : Serene Terrace slab completed – Status as of February 2021

Serene Tower E - G Low-rise : Serene Terrace Floor slab completed – Status as of February 2021

Serene Tower B - C Low-rise : Serene First floor slab structure works in progress – Status as of February 2021

All Serene Towers : Flooring commenced – Status as of February 2021

Eden Tower A : Part 14th & 16th Floor structure works in progress – Status as of February 2021

Eden Tower B : Part 5th Floor structure work in progress – Status as of February 2021

Eden Tower C : Part 13th & 20th Floor structure works in progress - Status as of February 2021

Eden Tower D : Part 6th Floor structure works in progress – Status as of February 2021

Eden Tower E : 20th floor structure works in progress – Status as of February 2021

Eden Towers A, C & E : Flooring Commenced – Status as of February 2021

Oasis Clubhouse : First floor structure works in progress – Status as of February 2021

Halcyon Tower I : Third floor slab work in progress & Halcyon Tower J : Part first floor slab work and part ground floor in progress – Status as of February 2021

Arcadia : Footings in podium area in progress. Podium part UB slab in progress – Status as of February 2021

Tranquil : Footings for Towers P & O in progress. Footings in Towers Q, K, L, M & N are completed UB slab in Towers Q, L & M in progress. UB slab in Tower K completed – Status as of February 2021

Serene Tower/Wing F : On Casting of 24th Floor Slab is completed – Status as of 27th February 2021

Serene Tower/Wing A : On Casting of 20th Floor Slab – Status as of 25th February 2021

Serene Tower/Wing E : On Casting of 24th Floor Slab – Status as of 25th February 2021

Serene Tower/Wing G : On Casting of 24th Floor Slab is completed - Status as of 25th February 2021

Tranquil Tower K : Milestone - Casting of Upper basement floor slab dt - Status as of 20th February 2021

Eden Tower C Milestone : On Completion of 12th floor slab - Status as of 19th February 2021

Serene Tower/Wing B : Commencement of flooring - Status as of 18th February 2021

Serene Tower/Wing C : Commencement of Flooring – Status as of 18th February 2021

Serene Tower/Wing E : Commencement of flooring - Status as of 18th February 2021

Serene Tower/Wing G : Commencement of flooring - Status as of 18th February 2021

Serene Tower/Wing B : On Casting of 20th Floor Slab is completed – Status as of 18th February 2021

Serene Tower/Wing H : On Casting of 24th Floor Slab - Status as of 18th February 2021

Serene Tower C : On Casting of 16th Floor Slab - Status as of 16th Feb 2021

Eden Wing A, C, E : Project Milestones - On Commencement of Flooring - Status as of 10th February 2021

Eden Wing A, C, E : Project Milestones - On Commencement of Flooring - Status as of 10th February 2021

Eden Wing A, C, E : Project Milestones - On Commencement of Flooring - Status as of 10th February 2021

Serene Wing A, D, F, H : Project Milestones - On Commencement of Flooring – 10th February 2021

Serene Wing A, D, F, H : Project Milestones - On Commencement of Flooring – 10th February 2021

Utopia Tranquil Project Milestone Tower N - On Casting of Footing/raft – 10th February 2021

Serene Tower A : 19th Floor slab structure works in progress. Serene Tower B : 19th Floor slab structure works in progress - Status as of January 2021

Serene Tower : C 15th Floor slab completed. Serene Tower : D 19th Floor slab structure works in progress - Status as of January 2021

Serene Tower E : 23rd Floor slab structure works in progress. And Serene Tower F : 22nd Floor slab structure works in progress - Status as of January 2021

Serene Tower G : 22nd Floor slab structure works in progress. Serene Tower H : 23rd Floor slab structure works in progress - Status as of January 2021

Serene Tower C - E Low-rise : Serene Terrace slab completed - Status as of January 2021

Serene Tower E - G Low-rise : Serene Terrace Floor slab completed - Status as of January 2021

Serene Tower B-C Low-rise : Serene First floor slab structure works in progress - Status as of January 2021

Eden Tower A : 12th Floor structure works under progress - Status as of January 2021

Eden Tower B : Part 5th Floor structure work in progress - Status as of January 2021

Eden Tower C : Part 11th & 18th Floor structure works in progress - Status as of January 2021

Eden Tower D : Part 6th Floor structure works in progress - Status as of January 2021

Eden Tower E : 17th floor structure works in progress - Status as of January 2021

Oasis - Clubhouse : Ground Floor and First floor structure works in progress – Status as of January 2021

Halcyon Tower I : First Floor and Second floor slab work in progress. And Halcyon Tower J : Ground floor slab work in progress – Status as of January 2021

Arcadia - Footings in podium area in progress and Podium part UB slab in progress – Status as of January 2021

Tranquil - Footings for Towers N & P in progress and Footings in Towers Q, K, L & M are completed - Status as of January 2021

Eden Tower/Wing E – On Casting of 16th Floor Slab is completed – Status as of 30th January 2021

Tranquil Tower M - On casting of footing / raft – Status as of 16th January 2021

Tranquil Tower M - On casting of footing / raft – Status as of 16th January 2021

Tranquil Tower M - On casting of footing / raft – Status as of 16th January 2021

Tranquil Tower M - On casting of footing / raft – Status as of 16th January 2021

Serene Tower / Wing F – On Casting of 20th Floor Slab is completed – 13th January 2021

Serene Tower / Wing F – On Casting of 20th Floor Slab is completed – 13th January 2021

Serene Tower / Wing G – Casting of 20th Floor Slab is completed – Status as of 8th January 2021

Serene Tower / Wing G – Casting of 20th Floor Slab is completed – Status as of 8th January 2021

Tranquil Tower L - On Casting of footing / raft - Status as of 8th January 2021

Serene Tower E - On Casting of 20th Floor Slab – 4th January 2021

Serene – View from central spine – Status as of December 2020

Serene Tower A : 18th Floor slab structure works in progress. And Serene Tower B : 17th Floor slab structure works in progress – Status as of December 2020

Serene Tower – C 15th Floor slab structure works in progress. And Serene Tower – D 18th Floor slab structure works in progress – Status as of December 2020

Serene Tower E - 20th Floor slab structure works in progress. And Serene Tower F 20th Floor slab structure works in progress – Status as of December 2020

Serene Tower G 20th Floor slab structure works in progress. And Serene Tower H 21st Floor slab structure works in progress – Status as of December 2020

Serene Tower C - E Low-rise : Serene Terrace slab completed – Status as of December 2020

Serene Tower E - G Low-rise : Serene Terrace Floor slab structure works in progress – Status as of December 2020

Eden Tower A - 10th Floor structure works under progress - Status as of December 2020

Eden Tower B – Part 5th Floor structure work in progress - Status as of December 2020

Eden Tower C – Part 11th & 15th Floor structure works in progress - Status as of December 2020

Eden Tower D – Part 5th Floor structure works in progress - Status as of December 2020

Eden Tower E – Part 12th & 14th floor structure works in progress - Status as of December 2020

Oasis Clubhouse - Oasis Ground Floor structure works in progress – Status as of December 2020

Halcyon Tower I : First Floor slab work in progress. And Halcyon Tower J : Ground floor slab work in progress – Status as of December 2020

Arcadia - Footings in podium area in progress - Podium part UB slab in progress – Status as of December 2020

Tranquil - Footings for Towers L, M, N & P in progress – Status as of December 2020

Eden Wing E - Project Milestones - On Casting of 12th floor slab - 31st December 2020

Serene B05 Tower/Wing B - On Casting of 16th Floor Slab - Status as of 27th December 2020

Halcyon - On Casting of Basement 01 Slab - Tower J - 22nd December 2020

Serene Tower/Wing H - On Casting of 20th Floor Slab – Status as of 20th December 2020

Serene Tower/Wing D – Casting of 16th Floor Slab is completed - 11th December 2020

Serene Tower/Wing A – Casting of 16th Floor Slab is completed - 11th December 2020

Tranquil Tower K - Completion of Footing / Raft Milestone - Status as of 11th December 2020

Tranquil Tower K - Completion of Footing / Raft Milestone - Status as of 11th December 2020

Tranquil Tower K - Completion of Footing / Raft Milestone - Status as of 11th December 2020

Halcyon Tower I - Casting of Ground floor Slab - Status as of 3rd December 2020

EDEN B03 Tower A - on casting of 8th floor slab – Status as of 1st December 2020

Tranquil - Retaining wall raft: 213/625 meters & Retaining Wall: 160/625 meter Completed. Total footings for K,L,M,N,O,P & Q towers – 93/419 No's completed. Tower Q - 47/47 footings completed. Columns – 39/551 No’s completed; PCC – 2000/6217 Sq.m - Status as of November 2020

Brigade Cornerstone Utopia Serene Towers – View from central spine - Status as of November 2020

Serene Tower A - 16th Floor slab structure works in progress & Serene Tower B - 15th Floor slab structure works in progress spine - Status as of November 2020

Serene Tower C – 14th Floor slab structure works in progress & Serene Tower D – 16th Floor slab structure works in progress - Status as of November 2020

Serene Tower E - 18th Floor slab structure works in progress & Serene Tower F - 18th Floor slab structure works in progress spine - Status as of November 2020

Serene Tower G - 18th Floor slab structure works in progress & Serene Tower H - 19th Floor slab structure works in progress - Status as of November 2020

Serene Tower C - E Low-rise : Serene Tower C & E Terrace slab completed - Status as of November 2020

Serene Tower E & G - 7th Floor slab structure works in progress - Status as of November 2020

Arcadia - Retaining wall raft – 180/375 Rmt  & Retaining wall – 180/375 Rmt completed. Footings : 57/121 No's completed & 36/139 No's column completed. Tower area footing PCC of 2600/2725 Sq. m completed – Status as of November 2020

Halcyon Tower I : Ground Floor slab work in progress & Tower J : First Basement slab work in progress - Status as of November 2020

Oasis - Ground Floor 1195 / 2300 Sq. m completed – Status as of November 2020

Eden Tower A - 9th Floor structure works under progress - Status as of November 2020

Eden Tower B – 4th Floor slab completed - Status as of November 2020

Eden Tower C – 12th & 13th Floor structure works under progress - Status as of November 2020

Eden Tower D – 5th Floor structure works under progress - Status as of November 2020

Eden Tower E – 12th Floor structure works under progress - Status as of November 2020

Eden Tower B - On Casting of fourth floor slab Completion - 30th November 2020

Tranquil Tower Q - Milestone - On Casting of Footing/raft – Status as of 23rd November 2020

Tranquil Tower Q - Milestone - On Casting of Footing/raft – Status as of 23rd November 2020

Tranquil Tower Q - Milestone - On Casting of Footing/raft – Status as of 23rd November 2020

Serene Wing G - On Casting of Sixteenth floor slab - Status as of 21st November 2020

Serene Wing F - On Casting of Sixteenth floor slab – Status as of 18th November 2020

Serene Wing E - On Casting of Sixteenth floor slab – Status as of 17th November 2020

Halcyon Tower J - On casting of Basement 2 floor Slab – Status as of 6th November 2020

Serene Wing C - On Casting of Twelfth floor slab - Status as of 3rd November 2020

Serene Towers Front view - Status as of October 2020

Serene Tower A - 14th Floor slab structure works in progress. Serene Tower B - 13th Floor slab structure in progress - Status as of October 2020

Serene Tower C - 12th Floor slab structure works in progress. Serene Tower C & D - 14th Floor slab structure works in progress - Status as of October 2020

Serene Tower E - 14th Floor slab structure works completed. Serene Tower F - 15th Floor structure works completed - Status as of October 2020

Serene Tower G - 14th Floor slab structure works completed. Serene Tower H - 16th Floor slab structure works completed - Status as of October 2020

Serene Tower C - E Low rise 9th Floor slab structure works completed - Status as of October 2020

Serene Tower E - G Low Rise 5th Floor slab structure works in progress - Status as of October 2020

Eden Tower A - 6th & 7th Floor structure works under progress - Status as of October 2020

Eden Tower B – 3rd Floor structure works under progress - Status as of October 2020

Eden Tower C - 11th Floor structure works under progress - Status as of October 2020

Eden Tower D - 5th Floor structure works under progress - Status as of October 2020

Eden Tower - E 10th Floor structure works under progress - Status as of October 2020

Serene B05 Tower / Wing H - On Casting of 16th Floor Slab - Status as of October 29th 2020

Eden Wing B - On Casting of Second Floor slab - Status as of 17th October 2020

Serene Wing B - On Casting of Twelfth floor slab - Status as of 17th October 2020

Serene Wing B - On Casting of Twelfth floor slab - Status as of 17th October 2020

Halcyon Tower I - On Casting of first basement slab - October 10th 2020

Oasis GF 670 / 2670 Sqm completed - Status as of October 2020

Oasis GF 670 / 2670 Sqm completed - Status as of October 2020

Halcyon Tower Basement - On Completion of 02 floor slab, 01 floor slab - Work in Progress and Tower J Basement 02 floor slab Work in Progress - Status as of October 2020

Arcadia - Total Estimated Qty – 85,000 Cum, Excavated Qty-55,000 Cum. Retaining wall raft – 108/375 Rmt & Retaining wall – 50/375 Rmt completed. Footing Progress 15/103 Nos completed & 7/117 Nos column completed - Status as of October 2020

Tranquil - Total Estimated Qty – 1,60,000 Cum, Excavated Qty – 1,30,000 Cum. Retaining wall raft in Q tower 40/585 Rmt. Q Tower PCC 600/6217 Sqm Completed - Status as of October 2020

Tranquil - Total Estimated Qty – 1,60,000 Cum, Excavated Qty – 1,30,000 Cum. Retaining wall raft in Q tower 40/585 Rmt. Q Tower PCC 600/6217 Sqm Completed - Status as of October 2020

Serene Tower A 12th Floor slab structure works completed. Tower B 11th Floor slab structure works completed – Status as of September 2020

Serene Tower – C 10th Floor slab structure works completed. Tower – D 12th Floor slab structure works completed – Status as of September 2020

Serene Tower E 14th Floor slab structure works completed. Tower - F 14th Floor slab structure works under progress – Status as of September 2020

Serene Tower G 13th Floor slab structure works completed. Tower H 14th Floor slab structure works completed – Status as of September 2020

Serene Tower C & E Low-rise - 8th Floor structure works under progress – Status as of September 2020

Serene G & E Extension - 4th Floor structure works under progress – Status as of September 2020

Serene B05 Tower/Wing A – Casting of 12th Floor Slab was completed on September 4th 2020

Eden Tower A Completion of Fourth floor slab Milestone - Status as of September 2020

Eden - Tower A - 4th & 5th Floor structure works under progress – Status as of September 2020

Eden Tower B - 3rd Floor structure works under progress - Status as of September 2020

Eden Tower C - 10th Floor structure works under progress - Status as of September 2020

Eden Tower D - 5th Floor structure works under progress - Status as of September 2020

Eden Tower E - 9th Floor structure works under progress - Status as of September 2020

Serene Wing D - On Casting of 12th floor slab – Status as of 30th September 2020

Eden Wing E - On Casting of 8th floor slab – Status as of 30th September 2020

Eden Tower D – On Casting of Fourth floor slab - Status as of 25th September 2020

Eden Tower C - On casting of 8th floor slab - Status as of 19th September - 2020

Serene Tower G - On Casting of 12th Floor Slab - 16th September 2020

Eden B03 Tower B - On Casting of 1st Floor Slab - 16th September 2020

Serene B05 Tower/Wing F - Casting of 12th Floor Slab is completed – Status as of September 2020

Project Milestones Utopia Serene Wing C - On Casting of Eighth floor slab – Status as of September 2020

Project Milestones Utopia Serene Wing C - On Casting of Eighth floor slab - Status as of September 2020

Project Milestones Utopia Serene Wing E - On Casting of Twelfth floor slab – Status as of September 2020

Project Milestones Utopia Serene Wing E - On Casting of Twelfth floor slab - Status as of September 2020

Project Milestones Utopia Serene Wing H - On Casting of Twelfth floor slab - Status as of September 2020

Front elevation view of the Serene block – Status as of August 2020

Serene Tower - Status as of August 2020

Serene Tower A 11th floor slab in progress & Tower B 10th floor slab completed – Status as of August 2020

Serene Tower C 8th floor slab in progress & Tower D 11th floor slab in progress - Status as of August 2020

Serene Tower E 12th floor slab in progress & Tower F 12th floor slab in progress - Status as of August 2020

Serene Tower G 12th floor slab in progress & Tower H 12th floor slab in progress - Status as of August 2020

Serene Low rise between C & E - 7th Floor slab work under progress - Status as of August 2020

Serene Low rise between G & E - 3rd Floor slab work under progress - Status as of August 2020

Eden Tower A - Part of 2nd Floor slab and part of 3rd floor slab in progress - Status as of August 2020

Eden Tower B – First floor slab in progress - Status as of August 2020

Eden Tower C - Part of 7th floor & part of 8th floor slab work in progress - Status as of August 2020

Eden Tower D - 4th floor slab work under progress - Status as of August 2020

Eden Tower E – Part of 6th floor slab work and part of 7th floor slab work under progress - Status as of August 2020

Eden Wing E - On Casting of Fourth floor slab - Status as of August 11th 2020

Eden Wing B - On Casting of Ground floor slab - Status as of August 5th 2020

Eden Wing B - On Casting of Ground floor slab - Status as of August 5th 2020

Halcyon Tower I : Basement - 2 completed. Basement-1 slab work in progress - Status as of August 2020

Halcyon Tower I & J : Basement - 3 columns and Basement - 2 slabs work in progress - Status as of August 2020

Club House - Oasis Basement structure work under progress - Status as of August 2020

Club House – Oasis Basement structure work under progress - Status as of August 2020

Cineplex & Retail - Arcadia Excavation Completed. Retaining wall work in progress - Status as of August 2020

Cineplex & Retail - Arcadia Excavation Completed. Retaining wall work in progress - Status as of August 2020

Tranquil Tower K, L, M, N, O, P & Q Excavation under progress - Status as of August 2020

Serene Tower A 9th floor slab in progress & Tower B 8th floor slab completed - Status as of July 2020

Serene Tower C 6th floor slab in progress & Tower D 9th floor slab in progress - Status as of July 2020

Serene Tower E 10th floor slab in progress & Tower F 10th floor slab in progress - Status as of July 2020

Serene Tower G 11th floor slab in progress & Tower H 10th floor slab in progress - Status as of July 2020

Serene Low rise between C & E Tower - 7th Floor slab work under progress - Status as of July 2020

Serene Low rise between G & E Tower - 3rd Floor slab work under progress - Status as of July 2020

Eden Tower A - Part of 2nd Floor slab and part of 3rd floor slab in progress - Status as of July 2020

Eden Tower B - Ground floor slab in progress - Status as of July 2020

Eden Tower C - 5th floor slab work in progress - Status as of July 2020

Eden Tower D - 3rd floor slab work under progress - Status as of July 2020

Eden Tower E - Part of 4th floor slab work and part of 5th floor slab work under progress - Status as of July 2020

Halcyon Tower I & J foundation completed - Status as of July 2020

Club House – Oasis Basement structure work under progress - Status as of July 2020

Club House – Oasis Basement structure work under progress - Status as of July 2020

Cineplex & Retail - Arcadia Excavation Completed - Status as of July 2020

Cineplex & Retail - Arcadia Excavation Completed - Status as of July 2020

Tranquil Tower K, L, M, N, O, P & Q Excavation under progress - Status as of July 2020

Tranquil Tower K, L, M, N, O, P & Q Excavation under progress - Status as of July 2020

Serene – Tower B – Casting of 8th Floor Slab Completion - 30th-July-2020

Serene – Tower B – Casting of 8th Floor Slab Completion - 30th-July-2020

Serene D - On casting of 8th floor slab - Status as of 14th-July-2020

Serene D - On casting of 8th floor slab - Status as of 14th-July-2020

Serene E - Casting of Eighth floor slab complete - Status as of 06-July-2020

Halcyon - Tower I & J Upper basement structure work under progress - Status as of June 2020

Tranquil - Tower K, L, M, N, O, P & Q Excavation under progress - Status as of June 2020

Oasis Club House - Basement structure work under progress - Status as of June 2020

Arcadia Cineplex & Retail - Excavation under progress - Status as of June 2020

Serene - Tower A & B - Tower A - 9th Floor & Tower B - 7th Floor structure works under progress - Status as of June 2020

Serene - Tower C & D - Tower C - 6th Floor & Tower D - 8th Floor structure works under progress - Status as of June 2020

Serene - Tower E & F - Tower E - 8th Floor & Tower F - 10th Floor structure works under progress - Status as of June 2020

Serene - Tower G & H, 10th Floor structure works under progress - Status as of June 2020

Serene – C & E Low-rise, 7th Floor structure works under progress - Status as of June 2020

Serene – Tower G & E, 3rd Floor structure works under progress - Status as of June 2020

Eden - Tower A - Second floor structure work under progress - Status as of June 2020

Eden - Tower B - Ground floor structure work under progress - Status as of June 2020

Eden - Tower C - Fifth floor structure work under progress - Status as of June 2020

Eden - Tower D - Casting of Second floor slab completed – Status as of 04-July-2020

Halcyon - Tower I - Raft completed - Status as of May 2020

Halcyon - Tower J - Raft work under progress - Status as of May 2020

Tranquil - Excavation work in Progress - Status as of May 2020

Tranquil - Excavation work in Progress - Status as of May 2020

Serene - Tower A - 8th Floor slab Casting Completed & Tower B - 5th Floor slab structure works under progress - Status as of May 2020

Serene - Tower C - 5th Floor slab structure works under progress - Status as of May 2020

Serene - Tower D - 8th Floor slab structure works in progress - Status as of May 2020

Serene - Tower E - 7th Floor slab structure works under progress - Status as of May 2020

Serene - Tower F - 9th Floor slab structure works under progress - Status as of May 2020

Serene - Tower G - 8th Floor slab structure work in progress & Tower H - 10th Floor slab structure works under progress - Status as of May 2020

Serene - C & E Low-rise - Tower C - 6th Floor slab structure works under progress - Status as of May 2020

Serene - Tower G & E low rise - Tower G - 3rd Floor slab structure works under progress - Status as of May 2020

Eden - Tower A - Part of First floor slab and part of Second Floor slab structural work in progress - Status as of May 2020

Eden - Tower B - Upper basement slab work in progress - Status as of May 2020

Eden - Tower C - Fourth floor slab structure work in progress - Status as of May 2020

Eden - Tower D - Part of First floor slab and part of second floor slab structure work in progress - Status as of May 2020

Eden - Tower E - Part of First floor slab and part of Second Floor slab structural work in progress - Status as of May 2020

Serene – B05 Tower/Wing F – Casting of 8th Floor Slab was completed - Status as of May 2020

Oasis – Ground floor slab shuttering work in progress - Status as of March 2020

Halcyon - Foundation work of Tower I and J in progress - Status as of March 2020

Arcadia - Excavation Completed - Status as of March 2020

Tranquil - Excavation in progress - Status as of February 2020

Serene - Tower A – 8th Floor Slab Work in progress - Status as of March 2020

Serene - Tower B – 4th Floor Slab Completed & 5th Floor Slab work in progress - Status as of March 2020

Serene - Tower C – 4th Floor Slab Completed & 5th Floor Slab work in progress - Status as of March 2020

Serene - Tower D – 8th Floor Slab Work in progress - Status as of March 2020

Serene - Tower E – 6th Floor slab works under progress - Status as of March 2020

Serene - Tower F – 8th Floor slab works in progress - Status as of March 2020

Serene - Tower G – 8th Floor slab works in progress - Status as of March 2020

Serene - Tower H – 8th Floor Slab Work Completed & 9th Floor slab works in progress - Status as of March 2020

Serene - Tower C & E – 6th Floor slab works in progress - Status as of March 2020

Serene - Tower G & E – 3rd Floor slab works under progress - Status as of March 2020

Eden - Tower A - First floor slab works under progress and Part of Second floor slab works under progress - Status as of March 2020

Eden - Tower B - Upper Basement slab work in progress - Status as of March 2020

Eden - Tower C - Third floor slab completed - Status as of March 2020

Eden - Tower D - Second floor slab half part of work is completed - Status as of March 2020

Eden - Tower E - First floor slab half part of work is completed, Second floor slab work under progress - Status as of March 2020

Oasis – Oasis – Excavation Completed , 38/51 Footing, 36/69 Columns upto UBL & 122 Rmt / 247 Rmt Retaining wall completed - under progress - Status as of February 2020

Halcyon - Excavation completed , 56/191 Footings, 12/245 Column upto UBL & Retaining wall raft 232/547 Rmt, Wall 179/547 Rmt completed - under progress - Status as of February 2020

Arcadia - Excavation Under Progress - 44,000 out of 80,000 Cum completed, PCC started on 26th Feb’20 - under progress - Status as of February 2020

Tranquil - Excavation Under Progress – 10,000 out of 1,60,000 Cum completed - under progress - Status as of February 2020

Serene - Tower A & B - Tower A – Gf to 5th Floor structure works Completed, 6th Floor, Tower B – GF to 4th Floor structure works Completed, 5th Floor under progress - Status as of February 2020

Serene - Tower C & D - Tower D – Gf to 6th Floor structure works Completed, 7th Floor, Tower C – GF to 4th Floor structure works Completed, 5th Floor under progress - Status as of February 2020

Serene - Tower C & E - GF to 3rd Floor structure works completed, 4th Floor - under progress - Status as of February 2020

Serene - Tower E & F - Tower F – Gf to 6th Floor structure works Completed, 7th Floor, Tower E – GF to 5th Floor structure works Completed, 6th Floor - under progress - Status as of February 2020

Serene - Tower G & H - Tower H – Gf to 7th Floor structure works Completed, 8th Floor, Tower G– GF to 5th Floor structure works Completed, 6th Floor - under progress - Status as of February 2020

Serene - Tower E & G - GF to 1st Floor structure works completed, 2nd Floor - under progress - Status as of February 2020

Eden - Tower A - Upper basement slab Completed - 100, GF Slab work is completed, 1st Floor floor slab – under progress - Status as of February 2020

Eden - Tower B - Footing Completed , STP Wall casted, UBL floor slab pour 1 casted – under progress - Status as of February 2020

Eden - Tower C - GF to 1st Floor structure works completed, 2nd Floor – under progress - Status as of February 2020

Eden - Tower D - GF to 1st Floor structure works completed, 2nd Floor – under progress - Status as of February 2020

Eden - Tower E - GF to 1st Floor structure works – under progress - Status as of February 2020

Oasis – Excavation Completed , 33/51 Footing & 34 Rmt / 247 Rmt Retaining wall completed - Status as of February 2020

Halcyon - Excavation completed , 11/188 Footing & Retaining wall raft 196/507 Rmt completed - Status as of January 31st 2020

Arcadia - Excavation Under Progress - 30,000 out of 80,000 Cum completed - Status as of January 31st 2020

Serene - Tower A & B - Footing, Back Filling, Grade Slab, Columns till Ground floor completed, Ground floor slab for Tower Completed, Tower A – Gf to 3rd Floor Completed, 4th Floor 2/6 Flats completed, Tower B – GF to 2nd Floor Completed, 3rd Floor under progress - Status as of January 31st 2020

Serene - Tower C & D - Footing, Back Filling, Grade Slab, Columns till Ground floor completed, Ground floor slab for Tower Completed,Tower D – Gf to 4th Floor Completed, 5th Floor under progress, Tower C – GF to 2nd Floor Completed, 3rd Floor under progress - Status as of January 31st 2020

Serene - Tower C & E - Footing Completed, Back Filling, Grade Slab, Columns till Upper Basement completed, upper basement floor slab completed, GF slab Completed GF to 1st Floor 5/5 Flats completed, 2nd Floor under progress - Status as of January 31st 2020

Serene - Tower E & F - Footing, Back Filling, Grade Slab, Columns till Ground floor completed, Ground floor slab for Tower Completed, Tower F – Gf to 4th Floor Completed, 5th Floor 2/6 Flats completed, Tower E – GF to 2nd Floor Completed, 3rd Floor under progress - Status as of January 31st 2020

Serene - Tower G & H - Footing, Back Filling, Grade Slab, Columns till Ground floor completed, Ground floor slab for Tower Completed, Tower H – Gf to 5th Floor Completed, 6th Floor under progress, Tower G– GF to 3rd Floor Completed, 4th Floor under progress - Status as of January 31st 2020

Serene - Tower G & E - Footing Completed, Back Filling, Grade Slab, Columns till Upper Basement completed, upper basement completed.GF Slab Completed, 1st Floor under progress - Status as of January 31st 2020

Eden Tower A - Footing, backfilling, grade slab completed, columns till upper basement completed, upper basement slab most of the work is Completed & GF Slab Work in progress - Status as of January 31st 2020

Eden - Tower B - Mass Excavation completed, Footing Completed , STP Walls on Progress - Status as of January 31st 2020

Eden - Tower C - Footings completed, columns till upper basement completed, UB Slab –Complete, GF Completed, 1st Floor Slab Pour-1 completed - Status as of January 31st 2020

Eden - Tower D - Footing, backfilling, grade slab completed, columns till upper basement completed, upper basement slab Completed, GF Slab Completed,1st Floor pour-1 completed - Status as of January 31st 2020

Eden - Tower E - Footing, backfilling, grade slab completed, columns till upper basement completed, Back filling Completed, UG Sump Raft Completed, UG Sump Walls & Slab Completed - Upper Basement almost work is Completed - Status as of January 31st 2020

Eden - Retaining Wall - 528/ 574 Rmt Retaining wall completed upto Upper Basement level, 119/574 Rmt Retaining wall completed upto GF level - Status as of January 31st 2020



© Brigade Cornerstone Utopia - 2021  |  About Brigade  |  Disclaimer

Enquire Now

Speak to us

Please select your country and enter your phone number

I Agree to the Terms & Conditions

Please wait..

Thank you for requesting a call back
Our team will get back to you shortly!