Status

Serene H Tower
On Casting of Eighth floor slab - Status as of March 2020

Oasis – Oasis – Excavation Completed , 38/51 Footing, 36/69 Columns upto UBL & 122 Rmt / 247 Rmt Retaining wall completed - under progress - Status as of February 2020

Halcyon - Excavation completed , 56/191 Footings, 12/245 Column upto UBL & Retaining wall raft 232/547 Rmt, Wall 179/547 Rmt completed - under progress - Status as of February 2020

Arcadia - Excavation Under Progress - 44,000 out of 80,000 Cum completed, PCC started on 26th Feb’20 - under progress - Status as of February 2020

Tranquil - Excavation Under Progress – 10,000 out of 1,60,000 Cum completed - under progress - Status as of February 2020

Serene - Tower A & B - Tower A – Gf to 5th Floor structure works Completed, 6th Floor, Tower B – GF to 4th Floor structure works Completed, 5th Floor under progress - Status as of February 2020

Serene - Tower C & D - Tower D – Gf to 6th Floor structure works Completed, 7th Floor, Tower C – GF to 4th Floor structure works Completed, 5th Floor under progress - Status as of February 2020

Serene - Tower C & E - GF to 3rd Floor structure works completed, 4th Floor - under progress - Status as of February 2020

Serene - Tower E & F - Tower F – Gf to 6th Floor structure works Completed, 7th Floor, Tower E – GF to 5th Floor structure works Completed, 6th Floor - under progress - Status as of February 2020

Serene - Tower G & H - Tower H – Gf to 7th Floor structure works Completed, 8th Floor, Tower G– GF to 5th Floor structure works Completed, 6th Floor - under progress - Status as of February 2020

Serene - Tower E & G - GF to 1st Floor structure works completed, 2nd Floor - under progress - Status as of February 2020

Eden - Tower A - Upper basement slab Completed - 100, GF Slab 100% completed, 1st Floor floor slab – under progress - Status as of February 2020

Eden - Tower B - Footing Completed , STP Wall casted, UBL floor slab pour 1 casted – under progress - Status as of February 2020

Eden - Tower C - GF to 1st Floor structure works completed, 2nd Floor – under progress - Status as of February 2020

Eden - Tower D - GF to 1st Floor structure works completed, 2nd Floor – under progress - Status as of February 2020

Eden - Tower E - GF to 1st Floor structure works – under progress - Status as of February 2020

Oasis – Excavation Completed , 33/51 Footing & 34 Rmt / 247 Rmt Retaining wall completed - Status as of February 2020

Halcyon - Excavation completed , 11/188 Footing & Retaining wall raft 196/507 Rmt completed - Status as of January 31st 2020

Arcadia - Excavation Under Progress - 30,000 out of 80,000 Cum completed - Status as of January 31st 2020

Serene - Tower A & B - Footing, Back Filling, Grade Slab, Columns till Ground floor completed, Ground floor slab for Tower Completed, Tower A – Gf to 3rd Floor Completed, 4th Floor 2/6 Flats completed, Tower B – GF to 2nd Floor Completed, 3rd Floor under progress - Status as of January 31st 2020

Serene - Tower C & D - Footing, Back Filling, Grade Slab, Columns till Ground floor completed, Ground floor slab for Tower Completed,Tower D – Gf to 4th Floor Completed, 5th Floor under progress, Tower C – GF to 2nd Floor Completed, 3rd Floor under progress - Status as of January 31st 2020

Serene - Tower C & E - Footing Completed, Back Filling, Grade Slab, Columns till Upper Basement completed, upper basement floor slab completed, GF slab Completed GF to 1st Floor 5/5 Flats completed, 2nd Floor under progress - Status as of January 31st 2020

Serene - Tower E & F - Footing, Back Filling, Grade Slab, Columns till Ground floor completed, Ground floor slab for Tower Completed, Tower F – Gf to 4th Floor Completed, 5th Floor 2/6 Flats completed, Tower E – GF to 2nd Floor Completed, 3rd Floor under progress - Status as of January 31st 2020

Serene - Tower G & H - Footing, Back Filling, Grade Slab, Columns till Ground floor completed, Ground floor slab for Tower Completed, Tower H – Gf to 5th Floor Completed, 6th Floor under progress, Tower G– GF to 3rd Floor Completed, 4th Floor under progress - Status as of January 31st 2020

Serene - Tower G & E - Footing Completed, Back Filling, Grade Slab, Columns till Upper Basement completed, upper basement completed.GF Slab Completed, 1st Floor under progress - Status as of January 31st 2020

Eden - Tower A - Footing, backfilling, grade slab completed, columns till upper basement completed, upper basement slab Completed -75% , GF Slab 40% completed - Status as of January 31st 2020

Eden - Tower B - Mass Excavation completed, Footing Completed , STP Walls on Progress - Status as of January 31st 2020

Eden - Tower C - Footings completed, columns till upper basement completed, UB Slab –Complete, GF Completed, 1st Floor Slab Pour-1 completed - Status as of January 31st 2020

Eden - Tower D - Footing, backfilling, grade slab completed, columns till upper basement completed, upper basement slab Completed, GF Slab Completed,1st Floor pour-1 completed - Status as of January 31st 2020

Eden - Tower E - Footing, backfilling, grade slab completed, columns till upper basement completed, Back filling Completed, UG Sump Raft Completed, UG Sump Walls & Slab Completed -90% for Upper Basement - Status as of January 31st 2020

Eden - Retaining Wall - 528/ 574 Rmt Retaining wall completed upto Upper Basement level, 119/574 Rmt Retaining wall completed upto GF level - Status as of January 31st 2020

Oasis – Excavation Completed , 22/49 Footing & 34 Rmt / 247 Rmt Retaining wall completed - Status as of December 31st 2019

Halcyon - Excavation 55,000 Cum out of 70,000 Cum , P.C.C for Retaining Wall Started - Status as of December 31st 2019

Arcadia - Excavation Under Progress -15,000 out of 80,000 Cum - Status as of December 31st 2019

Serene - Tower A & B - Footing, Back Filling, Grade Slab, Columns till Ground floor completed, Ground floor slab for Tower Completed, Tower A – Gf to 1st Floor – Completed, 2nd Floor Completed, 3rd Floor 2/6 Flats Completed, Tower B – GF to 1st Floor Completed, 2nd Floor under Progress - Status as of December 31st 2019

Serene - Tower C & D - Footing, Back Filling, Grade Slab, Columns till Ground floor completed, Ground floor slab for Tower Completed, Tower D – Gf to 1st Floor – Completed, 2nd Floor Completed, 3rd Floor 2/6 Flats Completed, Tower C – GF to 1st Floor Completed, 2nd Floor under Progress - Status as of December 31st 2019

Serene - Tower E & F - Footing, Back Filling, Grade Slab, Columns till Ground floor completed, Ground floor slab for Tower Completed, Tower F – Gf to 1st Floor – Completed, 2nd Floor Completed , 3rd floor Completed , 4th Floor Under Progress, Tower E – GF to 1st Floor Completed, 2nd Floor under Progress - Status as of December 31st 2019

Serene - Tower G & H - Footing, Back Filling, Grade Slab, Columns till Ground floor completed, Ground floor slab for Tower Completed, Tower H – Gf to 1st Floor – Completed, 2nd Floor Completed , 3rd floor Completed , 4th Floor Under Progress, Tower G– GF to 1st Floor Completed, 2nd Floor under Progress - Status as of December 31st 2019

Serene - Tower C & E - Footing Completed, Back Filling, Grade Slab, Columns till Upper Basement completed, upper basement floor slab completed, GF slab Completed, GF to 1st Floor Under Progress (S-form) - Status as of December 31st 2019

Serene - Tower G & E - Footing Completed, Back Filling, Grade Slab, Columns till Upper Basement completed, upper basement completed.GF Slab under Progress - Status as of December 31st 2019

Eden - Tower A - Footing, backfilling, grade slab completed, columns till upper basement completed, upper basement slab Completed -75% , GF Slab Under Progress - Status as of December 31st 2019

Eden - Tower B - Mass Excavation completed, Footing Completed , STP Walls on Progress - Status as of December 31st 2019

Eden - Tower C - Footings completed, columns till upper basement completed, UB Slab –Complete, GF Completed, 1st Floor Slab Under Progress (S-form) - Status as of December 31st 2019

Eden - Tower C - Footing, backfilling, grade slab completed, columns till upper basement completed, upper basement slab Completed, GF Slab Completed,1st Floor Under Progress - Status as of December 31st 2019

Eden - Tower D - Footing, backfilling, grade slab completed, columns till upper basement completed, upper basement slab Completed, GF Slab Completed,1st Floor Under Progress - Status as of December 31st 2019

Eden - Tower E - Footing, backfilling, grade slab completed, columns till upper basement completed, Back filling Completed, UG Sump Raft Completed, UG Sump Walls & Slab Completed -60% for Upper Basement - Status as of December 31st 2019

Halcyon - Excavation under Progress – 44000/ 70000 Cum Completed , Civil Work yet to start

Serene - Tower A & B - Footing, Back Filling, Grade Slab, Columns till Ground floor completed Ground floor slab for Tower Completed, Tower A – Gf to 1st Floor – Completed, 2nd Floor Under progress, Tower B – GF to 1st Floor Under Progress - Status as of December 2019

Serene - Tower C & D - Footing, Back Filling, Grade Slab, Columns till Ground floor completed Ground floor slab for Tower Completed, Tower A – Gf to 1st Floor – Completed, 2nd Floor Under progress, Tower B – GF to 1st Floor Under Progress - Status as of December 2019

Serene - Tower E & F - Footing, Back Filling, Grade Slab, Columns till Ground floor completed, Ground floor slab for Tower Completed, Tower F – Gf to 1st Floor – Completed, 2nd Floor Completed , 3rd floor Under Progress (S-form), Tower E – GF to 1st Floor Under Progress (S-form) - Status as of December 2019

Serene - Tower G & H - Footing, Back Filling, Grade Slab, Columns till Ground floor completed, Ground floor slab for Tower Completed, Tower H – Gf to 1st Floor – Completed, 2nd Floor Completed , 3rd floor Under Progress (S-form), Tower G– GF to 1st Floor Under Progress (S-form) - Status as of December 2019

Eden - Tower A - 23/26 Footings completed, 42/65 Nos Columns Completed, Upper Basement 30% Completed, Balance Slab & Lift Area under Progress - Status as of December 2019

Eden - Tower D - Footing, backfilling, grade slab completed, columns till upper basement completed, upper basement slab Completed, GF 50% Slab Completed, Balance 50% Under Progress

Eden - Tower D - Footing, backfilling, grade slab completed, columns till upper basement completed, upper basement slab Completed, GF 50% Slab Completed, Balance 50% Under Progress - Status as of December 2019

Eden - Tower E - Footing, backfilling, grade slab completed, columns till upper basement completed, slab formwork under progress for UB level, Back filling Completed, UG Sump Raft Completed, UG Sump Walls Under Progress - Status as of December 2019

Serene - Tower A & B - Ground floor slab Completed - Status as of November 2019

Serene - Tower C & D - Upper basement floor slab completed for Tower C and Ground Floor slab completed for Tower D - Status as of November 2019

Serene - Tower E & F - Ground Floor Slab completed - Status as of November 2019

Serene - Tower G & H - Ground Floor Slab completed, 1st floor slab in progress - Status as of November 2019

Eden - Tower D - Raft completed - Status as of November 2019

Eden - Tower E - Raft under progress - Status as of November 2019

Eden - Tower A - Raft under progress - Status as of November 2019

Eden - Tower C - Raft under progress - Status as of November 2019

Serene - Tower A & B - Raft & Upper basement floor slab completed, Ground floor slab in Progress - Status as of October 2019

Serene - Tower C & D - Raft & Upper basement floor slab completed, Ground floor slab in Progress - Status as of October 2019

Serene - Tower E & F - Tower – E- Raft & Upper basement floor slab completed, Ground floor slab in Progress Tower – F - Raft & Upper basement floor slab completed, Ground floor slab completed - Status as of October 2019

Serene - Tower G & H - Raft & Upper basement floor slab, Ground floor slab completed and First floor slab is in Progress - Status as of October 2019

Eden - Tower D - Raft completed , upper basement slab in progress - Status as of October 2019

Eden - Tower E - Raft in progress - Status as of October 2019

Eden - Tower A - Raft in progress - Status as of October 2019

Eden - Tower C - Raft in progress - Status as of October 2019

Serene - Tower A & B - Upper Basement Slab casted for both the towers - Status as of August 2019

Serene - Tower C & D - Upper Basement Slab casted for both the towers - Status as of August 2019

Serene - Tower E & F - Upper Basement Slab casted for both the towers - Status as of August 2019

Serene - Tower G & H - Tower H Upper Basement Slab casted - Tower G Ground floor Slab Completed - Status as of August 2019

Eden - Tower A - Mass excavation completed. PCC works in progress - Status as of August 2019

Eden - Tower B - Excavation in progress - Status as of August 2019

Eden - Tower C - Footings and Column works for Lower Basement in progress - Status as of August 2019

Eden - Tower D - Footings and Column works for Lower Basement in progress - Status as of August 2019

Eden - Tower E - Footings and Column works for Lower Basement in progress - Status as of August 2019

Eden - D Block - Status as of August 2019

Eden - E Block - Status as of August 2019

Serene - A & B Block - Status as of August 2019

Serene - C & D Block - Status as of August 2019

Serene - E & F Block - Status as of August 2019

Serene - E & F_1 - Status as of August 2019

Serene - G & H _1 Block - Status as of August 2019

Serene - G & H Block - Status as of August 2019

Serene - R1 Block - Status as of August 2019

Serene - R2 Block - Status as of August 2019

Serene - R2_1 Block - Status as of August 2019

Serene - R3 Block - Status as of August 2019

A & B PCC of 300 Sqm staging is in progress - Status as of July 2019

Tower C & D PCC of 150 Sqm ready to take up form work - Status as of July 2019

E & F PCC 100 Sqm completed and staging work started - Status as of July 2019

G & H – Tower G slab is ready for concreting by 5th July 19 Tower H back filling 95 % completed and PCC of 330 Sqm completed and staging work started - Status as of July 2019

Serene North west corner progress - Status as of July 2019

Ribbon-01 – out of 33 footing 4 is completed 40% PCC completed - Status as of July 2019

Ribbon-02 out of 46 - 6 footing ready for concreting - Status as of July 2019

Ribbon-03 in 29 footing 15 footing and 4 column completed - Status as of July 2019

Tower G slab curing work progress - Status as of July 2019

Tower G from B1 to Podium column progress - Status as of July 2019

Eden Tower D & E PCC for footing 800 Sqm and 10 no footing concrete completed - Status as of July 2019

Eden Tower D & E PCC for footing 800 Sqm and 10 no footing concrete completed - Status as of July 2019



© Brigade Cornerstone Utopia - 2020  |  About Brigade  |  Disclaimer

Enquire Now

Speak to us

Please select your country and enter your phone number

Please wait..

Thank you for requesting a call back
Our team will get back to you shortly!