Status

Serene - Tower A & B - Raft & Upper basement floor slab completed, Ground floor slab in Progress - Status as of October 2019

Serene - Tower C & D - Raft & Upper basement floor slab completed, Ground floor slab in Progress - Status as of October 2019

Serene - Tower E & F - Tower – E- Raft & Upper basement floor slab completed, Ground floor slab in Progress Tower – F - Raft & Upper basement floor slab completed, Ground floor slab completed - Status as of October 2019

Serene - Tower G & H - Raft & Upper basement floor slab, Ground floor slab completed and First floor slab is in Progress - Status as of October 2019

Eden - Tower D - Raft completed , upper basement slab in progress - Status as of October 2019

Eden - Tower E - Raft in progress - Status as of October 2019

Eden - Tower A - Raft in progress - Status as of October 2019

Eden - Tower C - Raft in progress - Status as of October 2019

Serene - Tower A & B - Upper Basement Slab casted for both the towers - Status as of August 2019

Serene - Tower C & D - Upper Basement Slab casted for both the towers - Status as of August 2019

Serene - Tower E & F - Upper Basement Slab casted for both the towers - Status as of August 2019

Serene - Tower G & H - Tower H Upper Basement Slab casted - Tower G Ground floor Slab Completed - Status as of August 2019

Eden - Tower A - Mass excavation completed. PCC works in progress - Status as of August 2019

Eden - Tower B - Excavation in progress - Status as of August 2019

Eden - Tower C - Footings and Column works for Lower Basement in progress - Status as of August 2019

Eden - Tower D - Footings and Column works for Lower Basement in progress - Status as of August 2019

Eden - Tower E - Footings and Column works for Lower Basement in progress - Status as of August 2019

Eden - D Block - Status as of August 2019

Eden - E Block - Status as of August 2019

Serene - A & B Block - Status as of August 2019

Serene - C & D Block - Status as of August 2019

Serene - E & F Block - Status as of August 2019

Serene - E & F_1 - Status as of August 2019

Serene - G & H _1 Block - Status as of August 2019

Serene - G & H Block - Status as of August 2019

Serene - R1 Block - Status as of August 2019

Serene - R2 Block - Status as of August 2019

Serene - R2_1 Block - Status as of August 2019

Serene - R3 Block - Status as of August 2019

A & B PCC of 300 Sqm staging is in progress - Status as of July 2019

Tower C & D PCC of 150 Sqm ready to take up form work - Status as of July 2019

E & F PCC 100 Sqm completed and staging work started - Status as of July 2019

G & H – Tower G slab is ready for concreting by 5th July 19 Tower H back filling 95 % completed and PCC of 330 Sqm completed and staging work started - Status as of July 2019

Serene North west corner progress - Status as of July 2019

Ribbon-01 – out of 33 footing 4 is completed 40% PCC completed - Status as of July 2019

Ribbon-02 out of 46 - 6 footing ready for concreting - Status as of July 2019

Ribbon-03 in 29 footing 15 footing and 4 column completed - Status as of July 2019

Tower G slab curing work progress - Status as of July 2019

Tower G from B1 to Podium column progress - Status as of July 2019

Eden Tower D & E PCC for footing 800 Sqm and 10 no footing concrete completed - Status as of July 2019

Eden Tower D & E PCC for footing 800 Sqm and 10 no footing concrete completed - Status as of July 2019



© Brigade Cornerstone Utopia - 2019  |  About Brigade  |  Disclaimer

Enquire Now

Speak to us

Please select your country and enter your phone number

Please wait..

Thank you for requesting a call back
Our team will get back to you shortly!